11.—(1) Network Rail may, for the purposes of the authorised works—
(a)form and lay out means of access, or improve existing means of access, in the locations specified in columns (1) and (2) of Schedule 7 (access to works); and
(b)with the approval of the highway authority, form and lay out such other means of access or improve existing means of access, at such locations within the Order limits as Network Rail reasonably requires for the purposes of the authorised works.
(2) If a highway authority fails to notify Network Rail of its decision within 28 days of receiving an application for approval under paragraph (1)(b), that highway authority is deemed to have granted approval.