The Network Rail (Suffolk Level Crossing Reduction) Order 2020

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about opening options

Opening OptionsExpand opening options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Time limit for exercise of powers of acquisition

26.—(1) After the end of the period of 5 years beginning on the day on which this Order comes into force—

(a)no notice to treat is to be served under Part 1 of the 1965 Act as applied to the acquisition of rights or easements over land by article 19 (application of Part 1 of the 1965 Act); and

(b)no declaration is to be executed under section 4 (execution of declaration) of the 1981 Act(1) as applied by article 20 (application of the 1981 Act).

(2) The powers conferred by article 21 (power to acquire new rights), article 22 (temporary use of land for construction of works) and article 23 (temporary use of land for maintenance of works) cease at the end of the period referred to in paragraph (1), except that nothing in this paragraph prevents Network Rail from remaining in possession of land after the end of that period, if the land was entered and possession of it was taken before the end of that period.