Statutory Instruments
Transport
Made
at 9.00 a.m. on 24th February 2020
Laid before Parliament
at 2.00 p.m. on 24th February 2020
Coming into force
16th March 2020
The Secretary of State, makes the following order in exercise of the powers conferred by sections 7(1), (2) and (9), 16B(1), (2), (3) and (5), 20(1), (2) and (8), 24(1), (2) and (8) of the Railways Act 1993(1) and sections 25(7) and 38(1) of the Railways Act 2005(2).
In accordance with sections 7(1), 16B(1) and 20(1) of the Railways Act 1993, the Secretary of State has consulted with the Office of Rail and Road(3).
1. This Order may be cited as the Greater Manchester (Light Rapid Transit System) (Exemptions) (Amendment) Order 2020 and comes into force on 16th March 2020.
2. In the Schedule to the Greater Manchester (Light Rapid Transit System) (Exemptions) Order 2013(4), for the map substitute the map in the Schedule to this Order.
Signed by authority of the Secretary of State for Transport
Vere
Parliamentary Under Secretary of State
Department for Transport
At 9.00 a.m. on 24th February 2020
Article 2
(This note is not part of the Order)
This Order relates to the Greater Manchester Light Rapid Transit System, also known as Metrolink (the “Metrolink network”).
The Order amends the Greater Manchester (Light Rapid Transit System) (Exemptions) Order 2013 (“the 2013 Order”) by replacing the map contained in the Schedule to that Order with a revised map of the Metrolink network (article 2). The revised map includes a short section of additional track and six new stations that are being constructed. The effect is to extend the exemptions granted by the 2013 Order to the extension of the Metrolink network, construction of which was authorised by the Transport for Greater Manchester (Light Rapid Transit System) (Trafford Park Extension) Order 2016 (S.I. 2016/1035).
A full explanation of the exemptions granted by the 2013 Order, which are extended by this Order, can be found in the Explanatory Note and the Explanatory Memorandum to the 2013 Order. An impact assessment has not been produced for this instrument as no cost to business or voluntary sectors is foreseen. An Explanatory Memorandum is available alongside the instrument on the website www.legislation.gov.uk.
1993 c. 43; section 7(1) was amended by the Transport Act 2000 (c. 38) (“the 2000 Act”), Schedule 17 paragraphs 1 and 2, the Railways and Transport Safety Act 2003 (c. 20) (“the 2003 Act”), Schedule 2 paragraphs 1 and 3, the Railways Act 2005 (c. 14) (“the 2005 Act”), Schedule 1 paragraph 1(1) and Schedule 13 (Part 1) and by S.I. 2015/1682, the Schedule, paragraph 1. Section 7(9) was amended by the 2005 Act, Schedule 1 paragraph 1(2). Sections 16A to 16I were inserted by the 2000 Act, section 223 and section 16B(1) was amended by the 2003 Act, Schedule 2 paragraphs 1 and 3, the 2005 Act, Schedule 1 paragraph 11(4) and by S.I. 2015/1682, the Schedule, (paragraph 1). Section 20(1) was amended by the 2000 Act, Schedule 27 paragraphs 17 and 23(1) and (2), the 2003 Act, Schedule 2 paragraphs 1 and 3 and by S.I. 2015/1682, the Schedule (paragraph 1). Section 20(2) was amended by the 2000 Act, Schedules 27 paragraphs 17 and 23(1) and (3) and 31 (Part IV). Section 24(1) and (2) was amended by the 2005 Act, Schedule 1 paragraph 14(1) and (2). Section 143(3) was amended by the 2005 Act, Schedule 11 paragraphs 1 and 15. The “appropriate facilities authority” is defined, for the purposes of section 16B to G, in section 16A3A) (inserted by the 2005 Act, Schedule 1, paragraph 11(3)). A definition of “appropriate designating authority” was inserted into section 23(3) of the Railways Act 1993, for the purposes of Part 1 of that Act, by Schedule 1, paragraph 13(4) of the 2005 Act.
2005 c. 14. “the national authority” is defined for the purposes of section 38(1) in section 38(2) of the 2005 Act.
Sections 7(1), 16B1(1) and 20(1) were amended by S.I. 2015/1682 to give effect to the Office of Rail Regulation’s change of name to the Office of Rail and Road
S.I. 2013/339, amended by S.I. 2015/187. The Schedule to the 2013 Order is introduced by article 2 of that Order, which defines “the Metrolink network” as the network constructed or to be constructed on the routes shown on the map in the Schedule.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including:
The data on this page is available in the alternative data formats listed: