PART 2WORK PROVISIONS
Supplementary powers
Protective work to buildingsI120
1
Subject to the following provisions of this article, the undertaker may at its own expense carry out such protective works to any building or structure lying within the Order limits as the undertaker considers necessary or expedient.
2
Protective works may be carried out—
a
at any time before or during the construction of any part of the authorised development in the vicinity of the building or structure; or
b
after the completion of that part of the authorised development in the vicinity of the building or structure at any time up to the end of the period of 5 years beginning with the date of final commissioning.
3
For the purpose of determining how the powers under this article are to be exercised the undertaker may enter and survey any building or structure falling within paragraph (1) and any land within its curtilage.
4
For the purpose of carrying out protective works under this article to a building or structure the undertaker may (subject to paragraphs (5) and (6))—
a
enter the building or structure and any land within its curtilage; and
b
where the works cannot be carried out reasonably conveniently without entering land which is adjacent to the building or structure but outside its curtilage, enter the adjacent land (but not any building erected on it) within the Order limits.
5
Before exercising—
a
a power under paragraph (1) to carry out protective works under this article to a building or structure;
b
a power under paragraph (3) to enter a building or structure and land within its curtilage;
c
a power under paragraph (4)(a) to enter a building or structure and land within its curtilage; or
d
a power under paragraph (4)(b) to enter and take possession of land,
the undertaker must, except in the case of emergency, serve on the owners and occupiers of the building, structure or land not less than 14 days' notice of its intention to exercise that power and, in a case falling within sub-paragraph (a), (c) or (d) specifying the protective works proposed to be carried out.
6
Where a notice is served under paragraph (5)(a), F1... (5)(c) or (5)(d), the owner or occupier of the building, structure or land concerned may, by serving a counter-notice within the period of 10 days beginning with the day on which the notice was served, require the question of whether it is necessary or expedient to carry out the protective works or to enter the building, structure or land to be referred to arbitration under article 42(3) (procedures in relation to certain approvals etc.).
7
The undertaker must compensate the owners and occupiers of any building, structure or land in relation to which powers under this article have been exercised for any loss or damage arising to them by reason of the exercise of those powers.
8
Where—
a
protective works are carried out to a building or structure under this article; and
b
within 5 years beginning with the date of final commissioning for that part of the authorised development in the vicinity of the building or structure it appears that the protective works are inadequate to protect the building or structure against damage caused by the construction, on operation or maintenance of that part of the authorised development,
the undertaker must compensate the owners and occupiers of the building or structure for any loss or damage sustained by them.
9
Nothing in this article relieves the undertaker from any liability to pay compensation under section 10(2) (further provision as to compensation for injurious affection) of the 1965 Act.
10
Any compensation payable under paragraph (7) or (8) must be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
11
In this article “protective works” in relation to a building means—
a
underpinning, strengthening and any other works the purpose of which is to prevent damage which may be caused to the building or structure by the construction, operation or maintenance of the authorised development; and
b
any works the purpose of which is to remedy any damage which has been caused to the building by the construction, operation or maintenance of the authorised development.