The Riverside Energy Park Order 2020

99.  Regardless of any provision in this Order or anything shown on any plan, the undertaker must not acquire any apparatus otherwise than by agreement, and before extinguishing any existing rights for Thames Water to use, keep, inspect, renew and maintain its apparatus within the Order limits, the undertaker must, with the agreement of Thames Water, create a new right to use, keep, inspect, renew and maintain the apparatus that is reasonably convenient for Thames Water, such agreement not to be unreasonably withheld or delayed and, in any event, shall be deemed to be given within 28 days, and to be subject to arbitration under article 42(3) (procedures in relation to certain approvals etc.).E+W

Commencement Information

I1Sch. 10 para. 99 in force at 1.5.2020, see art. 1