Notification from the undertakerE+W
33. Prior to the pre–commencement works, Cory Environmental Holdings Limited or a person to whom the benefit of this Order has been transferred under article 9 (consent to transfer benefit of the Order) (as applicable) must notify the relevant planning authority that they are the undertaker for the purposes of this Order and, as the undertaker, has the benefit of [F1the provisions of this Order] pursuant to article 8 as well as the liabilities and obligations under this Order.
Textual Amendments
F1Words in Sch. 2 para. 33 substituted (10.3.2021) by The Riverside Energy Park (Correction) Order 2021 (S.I. 2021/273), art. 1(2), Sch.
Commencement Information
I1Sch. 2 para. 33 in force at 1.5.2020, see art. 1