PART 2WORKS PROVISIONS

Supplemental powers

Removal of vessels21

1

If it appears to the undertaker necessary or convenient to do so for the purposes of the construction or maintenance of the authorised development it may, with the consent of the harbour authority (such consent not to be unreasonably withheld), remove from within the Order limits, any vessel that is—

a

sunk, stranded or abandoned; or

b

moored or laid up (whether lawfully or not),

and relocate it to such place outside the Order limits (and if that is elsewhere within Lowestoft Harbour, to such place as is agreed by the harbour master) where it may without injury to the vessel be moored or laid.

2

Before exercising the powers conferred by paragraph (1), the undertaker must take such steps as it considers appropriate in the circumstances, in consultation with the harbour authority, to publish and display notices setting out—

a

the reason for requiring removal of any vessel from within that part of the limits of dredging specified in the notice; and

b

the date by which the vessel specified in the notice must be removed from that part of Lake Lothing within the Order limits also specified in the notice.

3

If the owner or master of any vessel within the Order limits does not remove that vessel from within the part of the Order limits specified in the notice before the date specified in accordance with paragraph (2)(b) the undertaker may, having first obtained consent from the harbour authority, cause that vessel to be removed.

4

Paragraph (2) does not apply in the case of an emergency, when the undertaker must in consultation with the harbour master take such steps as it considers practicable in the circumstances to inform persons of the proposed removal of any vessel from any part of Lake Lothing within the Order limits.

5

The undertaker may recover as a debt from the owner of any vessel removed pursuant to paragraph (3) all expenses incurred by the undertaker in respect of its removal.