Protection against dredging by the harbour authorityE+W

45.—(1) The harbour authority must not undertake a capital dredge in Lake Lothing within the limits of dredging without first submitting the plans of the proposed dredging operation to the undertaker for its approval.

(2) Approval under paragraph (1) is not to be unreasonably withheld by the undertaker and approval is deemed to have been granted if the undertaker fails to notify the harbour authority of its decision within 28 days of the submission of the plans.

(3) The harbour authority must carry out the dredging in accordance with the plans approved under this article or settled by arbitration under article 62 (arbitration).

(4) The harbour authority must notify the undertaker at least 5 days before undertaking any maintenance dredge in Lake Lothing within the limits of dredging.