Conditions on exemptions5
The exemption granted by article 3(b) of this Order is subject to compliance with the following conditions—
a
Rookery South Energy Recovery Facility is connected to the total system;
b
Rookery South Energy Recovery Facility does not export more than 100 megawatts of electrical power to the total system, except in circumstances outside the reasonable control of Rookery South Limited; and
c
Rookery South Limited is not a licensed generator.