PART 6FOR THE PROTECTION OF THE SI GROUP

1.  The provisions of this Part of this Schedule have effect, unless otherwise agreed in writing between the undertaker and SI Group.

2.  In this Part of this Schedule and notwithstanding the definitions contained in article 2 (interpretation)—

“environmental permit” means the permit issued by the Environment Agency to SI Group under reference EPR/BS47071B (as varied) in respect of the SI facility and the SI land;

“Four Ashes Limited” means Four Ashes Limited whose company number is 09747871 and whose registered office is 4th floor, 7/10 Chandos Street, Cavendish Square, London, W1G 9DQ;

“permits” means the environmental permit and a licence to abstract groundwater under reference number MD/028/0003/002 which inter alia govern the abstraction of contaminated groundwater and discharge to a wastewater treatment plant at the SI facility;

“SI facility” means the land edged blue for indicative purposes only on the SI facility plan;

“SI facility plan” means the plan referred to as such in Schedule 15 (certification documents) and certified as the SI facility plan by the Secretary of State for the purposes of this Order;

“SI land” means the land within the Order limits which is owned by the SI Group for so long as it is owned by it; and

“written agreement of SI” means—

(a)

the agreement dated 3 August 2018 between the SI Group and Four Ashes Limited; or

(b)

such other written agreement made between the SI Group and Four Ashes Limited from time to time.

3.  Subject to paragraph 7(1) of this Part of this Schedule the undertaker must not exercise any powers in accordance with this Order or the powers conferred by section 11(3) (powers of entry) of the 1965 Act in respect of the SI Group’s interests in the SI land or SI facility, or those interests which benefit those interests, including all rights, wayleaves and easements enjoyed by the SI Group in relation to the SI land and/or SI facility pursuant to—

(a)article 13 (accesses);

(b)article 21 (discharge of water);

(c)article 22 (authority to survey and investigate the land);

(d)article 24 (compulsory acquisition of land);

(e)article 25 (compulsory acquisition of rights);

(f)article 28 (private rights);

(g)article 29 (power to override easements and other rights);

(h)article 33 (rights under and over streets);

(i)article 34 (temporary use of land for carrying out the authorised development);

(j)article 35 (temporary use of land for maintaining the authorised development); and/or

(k)article 41 (felling or lopping trees and removal of hedgerows),

unless the exercise of such powers is in accordance with the written agreement of SI.

4.  The undertaker must not take any steps in accordance with this Order or otherwise that give rise to SI Group being in breach of any permits.

5.  The undertaker must not carry out any of the authorised development on any part of the SI land where that land remains encompassed within the site boundary regulated by and referred to in the environmental permit save as in accordance with the written agreement of SI.

6.  The undertaker must not, save as in accordance with the written agreement of SI., interfere with or obstruct the free, uninterrupted and safe use of any vehicular access to the SI facility.

7.  A power referred to in paragraphs 3, 5 and 6 of this Part of this Schedule may be exercised notwithstanding those paragraphs where the written agreement with SI to which they refer provides that the power is permitted to be exercised.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources