Search Legislation

The West Midlands Rail Freight Interchange Order 2020

Changes over time for: SCHEDULE 2

 Help about opening options

Version Superseded: 21/10/2020

Alternative versions:

Status:

Point in time view as at 25/05/2020.

Changes to legislation:

There are currently no known outstanding effects for the The West Midlands Rail Freight Interchange Order 2020, SCHEDULE 2. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Article 2

SCHEDULE 2U.K.REQUIREMENTS

PART 1 U.K.GENERAL REQUIREMENTS

InterpretationU.K.

1.  In this Part of this Schedule unless the context requires otherwise—

demolition and construction traffic management plan” means the document of that description contained in appendix N of technical appendix 15.1 of the environmental statement;

design and access statement” means the document of that description referred to in Schedule 15 (certification documents) and certified by the Secretary of State as the design and access statement for the purposes of this Order;

development zone parameters plan” means the plans of that description identified as document 2.5 and included in the parameters plans;

flood risk assessment” means the document of that description contained in technical appendix 16.1 of the environmental statement;

framework ecological mitigation and management plan” means the document of that description contained in technical appendix 10.4 of the environmental statement;

green infrastructure parameters plan” means the plans of that description identified as document 2.7 and included in the parameters plans;

lighting strategy and lighting impact assessment” means the document of that description contained in technical appendix 12.8 of the environmental statement;

map of heritage receptors” means the document of that description contained in technical appendix 9.2 of the environmental statement;

outline demolition and construction environmental management plan” means the document of that description contained in technical appendix 2.3 of the environmental statement;

outline written scheme of investigation” means the document of that description contained in technical appendix 8.5 of the environmental statement;

permissive paths” means those paths identified as such on the access and rights of way plans;

site-wide surface water drainage strategy” means the document of that description contained in technical appendix 16.3 of the environmental statement; and

water framework directive assessment” means the document of that description contained in technical appendix 16.2 of the environmental statement.;

Time limitU.K.

2.  The authorised development must not commence later than the expiration of 5 years beginning with the date that this Order comes into force.

Phases of developmentU.K.

3.—(1) The authorised development (excluding archaeological investigation, soil movement, geotechnical or ground contamination investigation) must not commence until a written scheme setting out all the phases of the authorised development, has been submitted to and approved in writing by the local planning authority.

(2) The approved phasing scheme must include phasing details of—

(a)earthworks;

(b)ecological mitigation;

(c)rail infrastructure;

(d)roads and bridges;

(e)surface water and foul drainage;

(f)development plots;

(g)landscaping, including mounding and acoustic fencing; and

(h)mains services.

(3) The approved phasing scheme can be subject to amendment by agreement with the local planning authority.

(4) The authorised development must be carried out in accordance with the approved phasing scheme as approved in writing by the local planning authority.

Detailed design approvalU.K.

4.—(1) No phase of the authorised development (excluding archaeological investigation, soil movement, geotechnical or ground contamination investigation) is to commence until details of that phase have been submitted to and approved in writing by the local planning authority. The details of each phase must be in general accordance with the design principles set out in section 7 of the design and access statement. Following the commencement of the authorised development the design principles set out in section 7 must be reviewed, updated if necessary, and agreed with the local planning authority following the occupation of 186,000 square metres of warehousing. Any revised design principles will apply to any phase of the development which has not been the subject of discussions pursuant to sub-paragraph (3) prior to the date of agreement of the revised design principles.

(2) The details of each phase must include details of the following where they are located within that phase—

(a)rail infrastructure and rail terminal;

(b)embankments and mounds;

(c)hard landscaping, cycle tracks, footpaths, bridleways and towpaths;

(d)advertisements for which advertisement consent under the 2007 Regulations would be required were it not for the provisions of article 45(5) of this Order;

(e)surface and foul drainage;

(f)bicycle, motorcycle and vehicle parking (including the location and quantum of electric charging points);

(g)built development design (including external materials and sustainable energy measures) and layout;

(h)site levels and finished floor levels;

(i)estate roads and other highway works except where such details have already been approved pursuant to Parts 2 and 3 of Schedule 13 (protective provisions);

(j)vehicular circulation routes;

(k)bridges;

(l)weighbridges;

(m)gatehouses;

(n)HGV parking and welfare facilities;

(o)fencing walls and other means of enclosure (including acoustic fencing);

(p)substations and relocated telecommunications masts; and

(q)the location of the pedestrian crossing on the A5/A449 link road notwithstanding the detail shown in that respect on the highway general arrangement plans (in consultation with the local highway authority and with the approval of Highways England)

(3) The details of any phase including the formation of screen bunds and/or buildings within Development Zones A4a and A5a as shown on the parameters plan must include a wind tunnel or other technical assessment of the likely effect of those detailed proposals on wind characteristics at Calf Heath Reservoir and any consequential effects on the suitability of the reservoir for sailing.

(4) Prior to carrying out any wind tunnel or other technical assessment in accordance with sub-paragraph (3), the undertaker must consult with the local planning authority and the Greensforge Sailing Club as to the scope, basis and methodology of such assessment.

(5) The details of any consequential effects on the suitability of the reservoir for sailing are to be taken into account by the local planning authority in deciding whether the detailed proposals referred to in sub-paragraph (3) should be approved; and, if requested, the undertaker must provide the local planning authority with appropriate guidance on the wind tunnel or other technical assessment so as to assist them in determining their decision-making on this matter.

(6) Draft details of each phase, required to be submitted in accordance with sub-paragraph (2), must be discussed with the local planning authority prior to being submitted for approval.

(7) No part of the authorised development comprised in Works No. 8 will be undertaken until details of the size and appearance of any buildings or other structures to be erected and details of any landscaping and hard surfacing have been submitted to and approved by the local planning authority.

(8) The details of the estate roads to be constructed to provide access to warehousing within Zone A7 must have regard to the desirability of minimising the impact on and loss of the existing hedgerows.

(9) Any warehouse erected within Zone A7 (as identified on the development zones parameters plan) must be single aspect so that the warehousing provides noise screening between the service yard/loading docks and noise sensitive receptors.

(10) The authorised development must be carried out in accordance with the details as approved in writing by the local planning authority.

Demolition and construction environmental management planU.K.

5.—(1) No phase of the authorised development (with the exception of the highway works which are governed by Parts 2 and 3 of Schedule 13 (protective provisions)) is to commence, including any preparatory earthworks or site levelling but excluding archaeological investigation, geotechnical or ground contamination investigation and ecological survey or mitigation works, until a demolition and construction environmental management plan (“DCEMP”) for that phase of development, drafted in accordance with the principles set out in the outline demolition and construction environmental management plan, has been submitted to and approved in writing by the local planning authority.

(2) The DCEMP for each phase must include—

(a)details of the methods to control noise arising from construction activities including—

(i)proposals for monitoring of construction noise;

(ii)proposals for the introduction of mitigation measures or alternative working practices where the measurements exceed acceptable limits; and

(iii)proposals for hours of construction and deliveries to and from the site;

(b)details of a dust management plan setting out the methods to be used to control dust and other emissions including smoke from the site;

(c)details of all temporary fencing, temporary buildings, compound areas and parking areas including arrangements for their removal following completion of construction;

(d)details of areas to be used for the storage of plant and construction materials;

(e)details of construction waste management including controlled wastes;

(f)details of the facilities to be provided for the storage of fuel, oil and other chemicals, including measures to prevent pollution;

(g)details of lighting arrangements for construction and site security purposes;

(h)advisory signage at public access points advising of possible hazards including the potential for sudden noise;

(i)details of any temporary surface water management system;

(j)details of existing and proposed landscaping which need to be protected during construction; and

(k)details for management of soils during the construction phases in accordance with the DEFRA Code of Practice for the Sustainable Use of Soil on Construction Sites 2009.

(3) The DCEMP for each phase of development is to be kept under review and updated if necessary as construction proceeds. Each DCEMP must be submitted by the undertaker for approval in writing by the local planning authority and any amendments must be agreed with the local planning authority. All construction works must be carried out in accordance with the DCEMP as approved.

RailU.K.

6.—(1) The undertaker must comply with the requirements in Part 2 of this Schedule.

(2) No authorised development may commence until a scheme for the continued provision of access to the West Coast Main Line has been agreed by the local planning authority, in consultation with Network Rail. Such a scheme is to include the specification of and timings for Network Rail's temporary and permanent access to the West Coast Main Line and show how access to the West Coast Main line will be maintained at all times.

(3) The authorised development is to be carried out in accordance with the details approved to the satisfaction of the local planning authority in consultation with Network Rail.

Construction hoursU.K.

7.—(1) Subject to sub-paragraphs (2) and (3), construction and demolition works (which for the purposes of this requirement excludes archaeological investigations and any non-intrusive internal fit-out works but must include start up and shut down and deliveries) must not take place other than between 07:00 and 18:30 hours on weekdays and 08:00 and 13:00 hours on Saturdays, and not at all on Sunday nor on bank holidays in England and Wales (under section 1 of the Banking and Financial Dealings Act 1971 M1), unless otherwise agreed in writing by the local planning authority.

(2) Subject to sub-paragraph (2), the following working is permitted outside the construction and demolition works' hours specified in sub-paragraph (1)—

(a)pre-planned construction works to highway or rail infrastructure requiring possessions where first notified to the local planning authority and local residents;

(b)emergency works; and

(c)works which do not cause noise that is audible at the boundary of the Order limits.

(3) Regardless of sub-paragraphs (1) and (2) no piling operations are to take place after 18:00 hours unless otherwise agreed in writing by the local planning authority.

(4) Any emergency works carried out under sub-paragraph (2)(b) must be notified to the local planning authority within 72 hours of their commencement.

Marginal Citations

Air quality – operational emissionsU.K.

8.—(1) No warehouse or rail terminal may be brought into use until details of any combustion plant, where the single or combined NOx emission rate is greater than 5mg/second, have been submitted to and approved in writing by the local planning authority. Where applicable, considering IAQM guidance (Guidance from Environmental Protection UK and the Institute of Air Quality Management for the consideration of air quality within the land-use planning and development control processes – January 2017), the details will be supported by an air quality assessment, which must outline mitigation measures if necessary.

(2) Any combustion plant must be installed and operated in accordance with manufacturers' instructions at all times.

ArchaeologyU.K.

9.—(1) No phase of the authorised development (with the exception of the highway works to the existing highways (the A5, the A449, Vicarage Road, Station Road and Station Drive) which are governed by Parts 2 and 3 of Schedule 13 (protective provisions)) is to commence until a written scheme of investigation for that phase has been submitted to and approved in writing by the local planning authority. The written scheme of investigation must be in accordance with the principles set out in the outline written scheme of investigation contained in technical appendix 8.5 of the environmental statement.

(2) The written scheme of investigation must provide for the investigation of areas of archaeological interest identified by the evaluation surveys which established the base line conditions in the environmental statement and include the following components, completion of each of which will trigger the phased discharging of the requirement—

(a)approval of a written scheme of investigation;

(b)where identified to be necessary, fieldwork in accordance with the agreed written scheme of investigation;

(c)completion of a post-fieldwork assessment report; to be submitted within 6 months of the completion of fieldwork, unless otherwise agreed in advance in writing by the local planning authority; and

(d)completion of analysis, preparation of site archive ready for deposition at a store approved by the local planning authority, production of an archive report, and submission of a publication report; to be completed within 2 years of the completion of fieldwork, unless otherwise agreed in advance in writing by the local planning authority.

(3) Any actions required by the written scheme of investigation must be carried out by a suitably qualified archaeologist in accordance with that approved scheme.

(4) The programme of archaeological work may be subject to alteration by approval in writing by the local planning authority.

Cultural heritage – demolition of heritage assetsU.K.

10.—(1) The undertaker must not demolish the Woodside Farm House and associated structures (as identified on the map of heritage receptors) before the commencement of development at Development Zones A6, A5b or A7c as shown on development zone parameter plan.

(2) The Woodside Farm House and associated structures must not be demolished until they have been subject to a scheme of historic building recording by suitably qualified professionals and written confirmation obtained from the local planning authority that the works required under sub-paragraph (4)(a) to (c) have been completed and have been submitted to the local planning authority.

(3) The scheme of historic building recording must be undertaken in accordance with a written scheme of investigation which will be submitted to and approved in writing by the local planning authority before the recording begins. The written scheme of investigation must set out the level of recording required in accordance with the ‘Understanding Historic Buildings: A Guide to Good Recording Practice’ guidance prepared by Historic England (May 2016, or latest edition at the time the written scheme of investigation is prepared).

(4) The written scheme of investigation must include the following components—

(a)the identification, description and methodology for the level of recording necessary for the Woodside Farm House and associated structures as per the Historic England guidance referred to in sub-paragraph (3);

(b)research on the heritage asset necessary to understand their historical and architectural interest which is proportionate to the level of recording identified;

(c)an on-site survey of the Woodside Farm House and associated structures in accordance with paragraph (a) and to include photography; and

(d)completed research and analysis for presentation in an illustrated historic building recording report to be submitted within 12 weeks of recording work on site. The report will be suitable for deposition at an archival store as directed and approved by the local planning authority.

(5) The archive referred to in sub-paragraph (4)(d) should be collated, ordered and indexed in accordance with the requirements of the Management of Research Projects in the Historic Environment (MoRPHE) (Historic England, 2015).

Cultural heritage – demolition of canal crossingsU.K.

11.  Demolition of the canal crossings (as identified on the development zone parameter plan) must be completed within 5 years of the commencement of the authorised development.

Ecological mitigation and management planU.K.

12.—(1) No phase of the authorised development which incorporates ecological mitigation or management is to commence until a written ecological mitigation and management plan for that phase has been submitted to and approved in writing by the local planning authority. The ecological mitigation and management plan must be in accordance with the principles set out in the framework ecological mitigation and management plan. The ecological mitigation and management plan may be subject to alteration by agreement in writing by the local planning authority.

(2) Any ecological mitigation and management plan approved under sub-paragraph (1) must include an implementation timetable and must be carried out as approved in writing by the local planning authority.

(3) If a phase does not include ecological mitigation or management then a statement from the undertaker must be provided to the local planning authority prior to the relevant phase being commenced, confirming that the phase includes no ecological mitigation or management and therefore no ecological mitigation and management plan is required for that phase pursuant to sub-paragraph (1).

(4) Where specified as required in the framework ecological mitigation and management plan, works must be supervised by a suitably qualified person or body.

Ground conditions – contamination riskU.K.

13.—(1) No phase of the authorised development (with the exception of the highway works to the existing highways (the A5, the A449, Vicarage Road, Station Road and Station Drive) which are governed by Parts 2 and 3 of Schedule 13 (protective provisions)) is to commence until a contamination report for that phase has been submitted to and approved in writing by the local planning authority.

(2) The contamination report will either—

(a)confirm that no further investigation is necessary for that phase of authorised development and, where applicable, what remedial measures are proposed (and detail how the remedial measures will be verified (a “verification plan”)) or confirm that no remedial measures are required for the particular phase of development; or

(b)include a written scheme of any further investigation considered necessary for that phase of the authorised development.

(3) Where further investigation is considered necessary under sub-paragraph (2)(b), the findings will be outlined in an assessment report to identify the extent of any contamination and, where applicable, any remedial measures to be taken to render the land fit for its intended purpose (and include details of a verification plan). The assessment report for that phase of the authorised development will be submitted to and approved in writing by the local planning authority.

(4) If, during the course of construction, previously unidentified contamination is discovered which potentially poses a significant risk to site occupants, controlled waters or ecological receptors, construction must cease on that localised area and the contamination must be reported in writing to the local planning authority within 10 working days. Prior to the recommencement of construction on that localised area, suitable investigation for the discovered contamination (to include any required amendments to the remedial measures) must be submitted to and approved in writing by the local planning authority. The authorised development must then be implemented in accordance with the details submitted to the local planning authority, unless otherwise agreed in writing by the local planning authority.

(5) Any contamination report, assessment report and any suitable investigation for discovered contamination referred to in this requirement related to the authorised development at Development Zones A1, B and/or C as shown on development zone parameter plan must be in accordance with the principles set out in the remediation safeguarding report.

14.—(1) No part of the authorised development (with the exception of the highway works to the existing highways (the A5, the A449, Vicarage Road, Station Road and Station Drive) which are governed by Parts 2 and 3 of Schedule 13 (protective provisions)) may be brought into use until either—U.K.

(a)if no remediation measures or verification plan was required under requirement 13 (ground conditions – contamination risk) a statement from the undertaker, or their approved agent, must be provided to the local planning authority, stating that no previously unidentified contamination was discovered during the course of development; or

(b)if remediation measures and verification plan were agreed under sub-paragraphs (2)(a) or (3) of requirement 12 (ecological mitigation and management plan), verification measures must be undertaken in line with the agreed verification plan for any works outlined in the remedial measures and a report showing the findings of the verification (a “verification report”) must be submitted to and approved in writing by the local planning authority.

(2) The verification report must—

(a)contain a full description of the works undertaken in accordance with the agreed remedial measures and verification plan; and

(b)demonstrate the effectiveness of the approved remedial measures.

EarthworksU.K.

15.  No phase of the authorised development (with the exception of the highway works to the existing highways (the A5, the A449, Vicarage Road, Station Road and Station Drive) which are governed by Parts 2 and 3 of Schedule 13 (protective provisions) and excluding archaeological investigation, geotechnical or ground contamination investigation and ecological mitigation works) is to commence until details of—

(a)the earthworks strategy relating to that phase of authorised development including the management and protection of soils;

(b)an earthworks specification for each phase of the authorised development;

(c)cutting slopes and embankment design that would accord with the approved earthworks specification;

(d)the extent of any material to be temporarily stored within the site;

(e)the use of the sand and gravel disturbed during the construction of the phase in connection with the authorised development; and

(f)any surplus material to be removed from the site for disposal or material to be imported to the site,

have been submitted to and approved in writing by the local planning authority. All earthworks must be carried out in accordance with the details as approved.

Landscape – written landscaping schemeU.K.

16.—(1) No phase of the authorised development containing landscaping mitigation is to commence until a written landscaping scheme for that phase (including the strategic landscaping included within that phase) has been submitted to and approved in writing by the local planning authority.

(2) The landscaping scheme must be in accordance with the green infrastructure parameters plan and must include details of all proposed soft landscaping works, including—

(a)location, number, species, size, layout, method of trees support, plant protection measures and planting density of any proposed planting;

(b)cultivation, importation of materials and other operations to ensure plant establishment;

(c)details of existing trees to be retained, with measures for their protection during the construction period in accordance with British Standard 5837:2012 “Trees in relation to Design, Demolition and Construction Recommendations”, and to include a schedule of remedial tree works to be carried out in accordance with British Standard 3998:2010 “Tree Works Recommendations” prior to construction commencing;

(d)a method statement and plan for the propagation, planting, establishment and maintenance of propagated Black Poplar specimens;

(e)the hedgerows which are to be retained;

(f)a canal enhancement scheme (for the relevant phase);

(g)a programme for the implementation of the works; and

(h)a landscape management plan setting out for a period of 20 years the arrangements for future maintenance including methods of funding and future monitoring, review and the maintenance of new trees, shrubs, hedgerows, woodlands and grassed areas and retained trees, shrubs, hedgerows, woodlands and grassed areas.

(3) Any written landscaping scheme approved under sub-paragraph (2) must include an implementation timetable and must be carried out as approved in writing by the local planning authority.

(4) If a phase does not include landscaping mitigation then a statement from the undertaker must be provided to the local planning authority prior to the relevant phase being commenced, confirming that the phase includes no landscaping mitigation and therefore no written landscaping scheme is required for that phase pursuant to sub-paragraph (1).

(5) The soft landscaping works in the vicinity of the “bat hop-overs” as identified on Figure A1.1 of the framework ecological mitigation and management plan must be in general accordance with the principles set out in the framework ecological mitigation and management plan and the bat hop-over structures must be erected prior to any new road to which they relate being brought into use.

Landscape – implementation and maintenance of landscaping worksU.K.

17.—(1) All landscaping works (with the exception of the highway works which are governed by Parts 2 and 3 of Schedule 13 (protective provisions)) must be carried out and maintained in accordance with the written landscaping scheme approved under requirement 16 (landscape – written landscaping scheme).

(2) Any tree or shrub planted as part of an approved landscape scheme that, within a period of 10 years after planting is removed, dies or becomes, in the opinion of the local planning authority, seriously damaged or diseased, must be replaced in the first available planting season with a specimen of the same species and size as that originally planted, unless the local planning authority gives consent to any variation.

Landscape – phasing of landscaping and ecology worksU.K.

18.  The undertaker must complete the landscaping works identified in column (2) of the following table by no later than the stage of the authorised development set out in column (3) of that table or such alternative later triggers as are agreed by the local planning authority.

(1) Item as identified on the green infrastructure parameters plan(2) Description(3) Stage of Authorised Development
(i)Croft Lane Community ParkTo be completed within 5 years of the commencement of the authorised development.
(ii)The ecological corridor linking Calf Heath Wood and Calf Heath ReservoirTo be completed within 5 years of the commencement of the authorised development, or prior to commencement of development at Development Zones A4a or A4b as shown on the green infrastructure parameters plan, whichever is sooner.
(iii)The southern section of Calf Heath Community ParkTo be completed prior to the commencement of development at Development Zones A4b as shown on the green infrastructure parameters plan.

Height of containersU.K.

19.  The height of any stack of containers within the Order limits must not exceed 12 metres.

Lighting detailsU.K.

20.—(1) No phase of the authorised development which incorporates artificial lighting is to commence until a lighting scheme with details of the proposed permanent external lighting in that phase has been submitted to and approved in writing by the local planning authority. The lighting scheme must accord with the principles established in the lighting strategy and lighting impact assessment but notwithstanding the content of the lighting strategy must have regard to the location and height of lighting columns in the vicinity of landscape bunds and screening. The lighting scheme must also accord with the ecological principles established in framework ecological management and mitigation plan.

(2) The approved lighting scheme must be implemented and maintained during operation of the authorised development and no external lighting other than that approved under this requirement may be installed.

(3) The highways lighting in the vicinity of the “bat hop-overs” as identified on Figure A1.1 of the framework ecological mitigation and management plan must be in accordance with the principles set out in the framework ecological management and mitigation plan.

(4) The details submitted under this requirement must include details of any lighting on any gantry cranes included in the phase concerned.

Noise – construction stageU.K.

21.—(1) For normal daytime construction and demolition works carried out on weekdays between 07:00 and 18:30 hours, the construction and demolition noise level measured at a noise sensitive receptor must not exceed Leq, 11hour 65 dB(A) and on Saturdays between 08:00 and 13:00 hours, the noise level measured at a noise sensitive receptor must not exceed Leq, 5 hour 65 dB(A) wherever practicable. Where this is not practicable, prior approval from the local authority must be sought, with full justification given for the deviation.

(2) Subject to health and safety requirements, broadband reversing alarms must be employed on mobile plant.

(3) In the event that complaints for noise nuisance are received by the local planning authority in respect of construction noise and the local planning authority considers those complaints justified, the undertaker must unless otherwise agreed by the local planning authority, at its own expense, employ a consultant approved by the local planning authority to carry out an assessment of noise from the development relating to noise from construction of the site. The assessment will be carried out to an appropriate methodology agreed in writing by the local planning authority and the results of the assessment will be submitted to the local planning authority within 28 days of the assessment. If it is found that the effect of noise from the authorised development is greater than was anticipated (as set out in paragraphs 13A.67 to 13A.82 of the addendum to Chapter 13 of the environmental statement), recommendations for appropriate remedial measures must be made and those recommendations, where reasonable, implemented in accordance with a programme agreed between the local planning authority and the undertaker.

Noise – operational stageU.K.

22.—(1) Prior to the occupation of any warehouse unit, details of all mechanical and ventilation plant must be submitted to and approved in writing by the local planning authority. Any fixed plant or ventilation equipment must be installed and operated in accordance with manufacturers' instructions at all times and the overall rating levels from all mechanical and ventilation plant should not exceed the limits set out in Table 13A.20 of the addendum to Chapter 13 of the environmental statement.

(2) The external walls of all warehouses must provide a minimum sound reduction of 39dB Rw and all warehouse roofs must provide a minimum sound reduction of 28dB Rw.

(3) Subject to health and safety requirements, broadband reversing alarms must be employed on site-based mobile plant and vehicles.

(4) In the event that complaints for noise nuisance are received by the local planning authority in respect of operational noise and the local planning authority considers those complaints justified, the undertaker must unless otherwise agreed by the local planning authority, at its own expense, employ a consultant approved by the local planning authority to carry out an assessment of noise from the development relating to noise from operation of the site. The assessment will be carried out to an appropriate methodology agreed in writing by the local planning authority and the results of the assessment will be submitted to the local planning authority within 28 days of the assessment. If it is found that the effect of noise from the authorised development is greater than was anticipated (as set out in paragraphs 13A.83 to 13A.133 of the addendum to Chapter 13 of the environmental statement), recommendations for appropriate remedial measures must be made and those recommendations, where reasonable, implemented in accordance with a programme agreed between the local planning authority and the undertaker.

Permissive pathsU.K.

23.—(1) No phase of the authorised development containing permissive paths is to commence until a scheme for the provision of the permissive paths in that phase has been submitted to and approved in writing by the local planning authority.

(2) The schemes referred to in sub-paragraph (1) must—

(a)set out the specification of the relevant permissive paths and timing of their provision;

(b)confirm the arrangements for ongoing maintenance of the relevant permissive paths;

(c)ensure public access to the relevant permissive paths at all time save for emergency closures and any closures required to maintain their permissive status; and

(d)make provision for the alteration to, or replacement of, the relevant permissive paths subject to the provision of suitable alternative arrangement.

(3) The approved permissive paths schemes must be implemented and maintained during operation of the authorised development.

Transport – demolition and constructionU.K.

24.—(1) The construction and demolition works must be carried out in accordance with the demolition and construction traffic management plan. The demolition and construction traffic management plan may be subject to alteration by agreement in writing by the local highway authority.

(2) No phase of the authorised development is to commence until a scheme for the provision, maintenance and subsequent removal of temporary signage for construction traffic in respect of that phase has been submitted to and approved by the local planning authority. The undertaker must provide, maintain and remove the temporary signage in accordance with the approved scheme.

Transport – phasing of highway worksU.K.

25.—(1) The undertaker must complete the highway works identified in columns (1) and (2) of the following table by no later than the stage of the authorised development set out in column (3) of that table or such alternative later triggers as are agreed by the relevant body or bodies identified in column (4) of that table.

(1) Item as identified on the highway general arrangement key plan / highways masterplan(2) Description(3) Stage of Authorised Development(4) Relevant Body
(i)A5 Access Roundabout, including works to Avenue Cottages junctionTo be completed prior to the occupation of first warehouse to be occupied (with the exception of less than 47,000 square metres (gross internal area) of warehouse floorspace accessed from the Vicarage Road Access Roundabout (item (iii)).Highways England / Staffordshire County Council
(ii)A5 – A449 link roadTo be completed prior to occupation of more than 140,000 square metres (gross internal area) of warehouse floorspace served via the A5 and 47,000 square metres (gross internal area) of warehouse floorspace served via the Vicarage Road Access Roundabout (item (iii)) or within five years of the occupation of more than 47,000 square metres (gross internal area) of warehouse floorspace, whichever is sooner.Highways England / Staffordshire County Council
(iii)Vicarage Road Access RoundaboutTo be completed prior to the occupation of any warehouse floorspace to accessed from the Vicarage Road Access Roundabout.Staffordshire County Council
(iv)Right turn ban and associated works at A449 / Station Drive junctionNot to be in force until such time as the A449 Roundabout (item xiv) has been completed.Highways England
(v)Crateford Lane closed to westbound trafficTo be completed prior to occupation of more than 140,000 square metres (gross internal area) of warehouse floorspace or within five years of the occupation of more than 47,000 square metres (gross internal area) of warehouse floorspace, whichever is sooner.Staffordshire County Council
(vi)Improved footway links along the A5 between Gailey Roundabout and the A5 Access RoundaboutTo be completed within 6 months of opening the A5 Access Roundabout.Highways England
(vii)Upgraded footway / cycleway on the A449 between Station Drive and Gailey RoundaboutTo be completed within 6 months of opening the A449 Access Roundabout.Highways England
(viii)Provide HGV turning area on Station Drive to the west of the rail bridgeTo be completed within 6 months of completing the Vicarage Road Access.Staffordshire County Council
(ix)Provide relocated A449 laybys to include closure of existing gaps in A449 Central Reservation and field accessesTo be completed prior to commencement of construction of A5 Access Roundabout.Highways England
(x)Improved visibility splay at Vicarage Road / Straight Mile Priority JunctionTo be completed prior to opening of Vicarage Road Roundabout.Staffordshire County Council
(xi)Provide footway and crossing improvements at Straight Mile / Kings Road / Woodlands LaneTo be completed prior to opening of network of permissive paths / community parks.Staffordshire County Council
(xii)Provide pedestrian crossing facilities at Straight MileTo be completed prior to opening of network of permissive paths / community parks.Staffordshire County Council
(xiii)Provide new Cycleway on Vicarage RoadTo be completed within 6 months of completing the Vicarage Road Access Roundabout.Staffordshire County Council
(xiv)A449 RoundaboutTo be completed prior to occupation of more than 140,000 square metres (gross internal area) of warehouse floorspace or within five years of the occupation of more than 47,000 square metres (gross internal area) of warehouse floorspace, whichever is sooner.Highways England

(2) At least two weeks prior to the anticipated date of each event/trigger specified in column (3) of the table in sub-paragraph (1) the undertaker must notify the relevant body identified in column (4) of that table of that anticipated date.

Water and flood risk – flood risk assessmentU.K.

26.  The authorised development must be carried out in accordance with the mitigation measures detailed within section 5.3 of the flood risk assessment or be carried out in accordance with any variation to these measures agreed in writing with the Environment Agency, the relevant local flood authority or the approving body under Schedule 3 (sustainable drainage) to the Flood and Water Management Act 2010 M2, whichever of these is the body having jurisdiction over the watercourse in question.

Marginal Citations

Water and flood risk – surface water drainage schemeU.K.

27.—(1) No phase of the authorised development (excluding archaeology works) is to commence until a surface water drainage scheme for that phase has been submitted to and approved in writing by the local planning authority or such other approval process that is put in place under the Flood and Water Management Act 2010. The surface water drainage scheme must be generally in accordance with the flood risk assessment and site-wide surface water drainage strategy and section 3.4 of the water framework directive assessment and must include a schedule of required maintenance activities (including frequency), and details of who is to be responsible for such maintenance, to ensure the continued performance of the system for the lifetime of the authorised development.

(2) Any surface water drainage scheme approved under sub-paragraph (1) (including, for the avoidance of doubt, the sustainable urban drainage component (SUDS)) must be implemented and maintained in accordance with the details approved by the local planning authority or in accordance with any variations to the details agreed in writing by the local planning authority prior to the completion of the relevant phase of the authorised development.

Water and flood risk – foul water drainageU.K.

28.—(1) Prior to the commencement of the development of any warehouse or the rail terminal, a foul water drainage scheme must be submitted to and approved in writing by the local planning authority.

(2) Any foul water drainage scheme approved under sub-paragraph (1) must be implemented in accordance with the details approved by the local planning authority or in accordance with any variations to the details agreed in writing by the local planning authority prior to the occupation of any warehouse unit or the rail terminal.

Building sustainabilityU.K.

29.—(1) No construction of a warehouse is to commence until a BREEAM pre-assessment report based upon the BREEAM 2011 method (or equivalent) has been submitted to and approved in writing by the local planning authority demonstrating that the warehouse is expected to achieve at least a BREEAM 2011 “Very Good” rating (BREEAM Industrial 2008 “Excellent”).

(2) The construction of each of the warehouses must be carried out in accordance with the details in the BREEAM pre-assessment report (or equivalent) for that warehouse and a certificate must be provided within three months of completion or occupation (whichever is the sooner) of each warehouse confirming that the measures in respect of that warehouse committed to within the pre-assessment report have been implemented.

Waste management during the operational phaseU.K.

30.  No warehouse, rail terminal or community park may be brought into use until a waste management scheme for that part of the authorised development during the operational phase has been submitted to and approved in writing by the local planning authority. Thereafter the approved scheme must be implemented and maintained for the duration of the operation of that part of the authorised development.

PART 2 U.K.RAIL REQUIREMENTS

InterpretationU.K.

31.  In this Part of this Schedule—

rail terminal works” means the works required to construct and provide a rail terminal capable of handling at least four trains a day;

rail terminal” means the rail terminal constructed as a result of and upon completion of the rail terminal works;

rail provision milestones” means the actions, and the timing related thereto, set out in requirements 40 and 41 (rail provision milestones);

undertaker” has the same meaning as sub-paragraph (a) of the definition of “undertaker” in article 2 (interpretation); and

“GRIP 3”, “GRIP 4” and “GRIP 5” relate to Network Rail's Governance for Rail Investment Projects current at the date of this order.

Rail ProvisionU.K.

32.  The undertaker must comply with all the rail provision milestones unless otherwise agreed with the local planning authority.

33.  The undertaker must keep the local planning authority advised of progress in respect of all the rail provision milestones on a quarterly basis including providing copies to the local planning authority of any material formally submitted to all bodies in pursuance of compliance with the rail provision milestones, if requested.U.K.

34.  The undertaker must notify the local planning authority of the date of the first occupation of more than 47,000 square metres of warehousing and 186,000 square metres of warehousing within 28 days of such occupations occurring.U.K.

Rail InfrastructureU.K.

35.  The undertaker must complete the rail terminal works prior to the earliest of—

(a)the occupation of more than 186,000 square metres of warehousing; or

(b)the sixth anniversary of the first occupation of more than 47,000 square metres of warehousing.

36.  The undertaker must pursue the completion of the rail terminal works as expeditiously as possible following the commencement of their construction.U.K.

37.  Following completion of the rail terminal works the undertaker must retain, manage and keep the rail terminal works available for use.U.K.

Rail SupportU.K.

38.  The undertaker must appoint a rail freight co-ordinator at least 3 months prior to the submission of the application for approval of GRIP 3 referred to in paragraph (1) of requirement 40 (rail provision milestones) who must report to the local planning authority no less than once a quarter on—

(a)the progress towards meeting the rail provision milestones;

(b)the progress of the rail terminal works; and

(c)the operation of the rail terminal when open including—

(i)the appointment of a rail operator to operate the rail terminal;

(ii)the amount of rail freight usage of the rail terminal;

(iii)the number of trains using the rail terminal;

(iv)the warehousing receiving or sending goods through the rail terminal; and

(v)the amount of goods being received or sent through the rail terminal by freight handlers not occupying the warehousing.

39.  The undertaker must maintain a person in the position of rail freight co-ordinator throughout the life of the authorised development unless otherwise agreed with the local planning authority.U.K.

Rail Provision MilestonesU.K.

40.—(1) The undertaker must submit an application to Network Rail for approval of the matters required to be considered as part of GRIP 3 by Network Rail prior to commencement of the authorised development and thereafter pursue such application expeditiously.

(2) The undertaker must submit an application to Network Rail for approval of the matters required to be considered as part of GRIP 4 by Network Rail within 3 months of the approval of the matters approved under sub-paragraph (1) and thereafter pursue such application expeditiously.

(3) The undertaker must identify and apply to Network Rail for the necessary track possessions required to enable the carrying out of the rail terminal works by no later than 14 days from approval of the matters approved under sub-paragraph (2) and thereafter pursue such application expeditiously.

(4) The undertaker must submit an application to Network Rail for approval of the matters required to be considered as part of GRIP 5 by Network Rail within 12 months of approval of the matters approved under sub-paragraph (2) and thereafter pursue such application expeditiously.

41.  The undertaker must progress the approvals referred to in paragraphs (a) to (d) as expeditiously as possible following the commencement of the authorised development—U.K.

(a)the approval of all of the detailed design information (as defined in paragraph 2 of Part 3 of Schedule 13 (protective provisions) for Works No. 4 (A5/A449 link road) pursuant to paragraph 3 of Part 3 of Schedule 13;

(b)the obtaining of a variation to the existing environmental permit issued under the Environmental Permitting (England & Wales) Regulations 2016 relating to the remediation of the SI land;

(c)the obtaining of any approvals required from Network Rail in connection with the construction of the rail terminal works pursuant to the provisions of Part 1 of Schedule 13; and

(d)the obtaining of all other consents required to lawfully construct the rail terminal works.

PART 3 U.K.PROCEDURE FOR APPROVALS ETC. UNDER REQUIREMENTS

InterpretationU.K.

42.  In this Part of this Schedule—

appeal documentation” means the application submitted to the discharging authority, any further information submitted under paragraph 44 and any notice of a decision to refuse;

the appeal parties” means the discharging authority, the undertaker and any requirement consultee(s);

discharging authority” means the authority from whom a consent, approval or agreement is required or requested by the undertaker under the requirement concerned;

requirement consultee” means any body named in a requirement which is the subject of an appeal as a body to be consulted by the discharging authority in discharging that requirement; and

working day” means a day other than Saturday or Sunday which is not Christmas Day, Good Friday or a bank holiday under section 1 (bank holiday) of the Banking and Financial Dealings Act 1971 M3.

Marginal Citations

Applications made for certain approvalsU.K.

43.—(1) Where an application has been made to a discharging authority for any consent, agreement or approval required or contemplated under the requirements in Part 1 of this Schedule the discharging authority must give notice to the undertaker of its decision on the application before the end of the decision period.

(2) For the purposes of sub-paragraph (1), the decision period is—

(a)where no further information is requested under paragraph 44, 42 days from the day immediately following that on which the application is received by the discharging authority;

(b)where further information is requested under paragraph 44, 42 days from the day immediately following that on which the further information has been supplied by the undertaker under paragraph 44; or

(c)such longer period as may be agreed by the undertaker and the discharging authority in writing before the end of the period in paragraph (a) or (b).

Further informationU.K.

44.—(1) In relation to any application to which this Schedule applies, the discharging authority has the right to request such further information from the undertaker as is necessary to enable it to consider the application.

(2) If the discharging authority considers such further information to be necessary it must, within 10 working days of receipt of the application, notify the undertaker in writing specifying the further information required.

(3) If the discharging authority does not give such notification as specified in sub-paragraph (2) it is to be deemed to have sufficient information to consider the application and is not subsequently entitled to request further information without the prior agreement of the undertaker.

AppealsU.K.

45.—(1) The undertaker may appeal in the event that—

(a)the discharging authority refuses an application for any consent, agreement or approval required or contemplated under the requirements or grants it subject to conditions;

(b)the discharging authority does not give notice of its decision to the undertaker within the decision period specified in paragraph 43;

(c)on receipt of a request for further information under paragraph 44 the undertaker considers that either the whole or part of the specified information requested by the discharging authority is not necessary for consideration of the application; or

(d)on receipt of any further information requested, the discharging authority notifies the undertaker that the information provided is inadequate and requests additional information which the undertaker considers is not necessary for consideration of the application.

(2) The appeal process is as follows—

(a)any appeal by the undertaker must be made within 42 days of the date of the notice of the decision or determination, or (where no determination has been made) expiry of the decision period as determined under paragraph 43;

(b)the undertaker must submit the appeal documentation to the Secretary of State and must within 7 working days provide copies of the appeal documentation to the discharging authority and the requirement consultees;

(c)as soon as is practicable after receiving the appeal documentation, the Secretary of State must appoint a person to determine the appeal (“the appointed person”) M4 and must notify the appeal parties of the identity of the appointed person and the address to which all correspondence for that person's attention should be sent;

(d)the discharging authority and the requirement consultees must submit written representations to the appointed person in respect of the appeal within 20 working days of the date on which the appeal parties are notified of the appointment of a person under paragraph (c) and must ensure that copies of their written representations are sent to each other and to the undertaker on the day on which they are submitted to the appointed person;

(e)the appeal parties must make any counter-submissions to the appointed person within 20 working days of receipt of written representations under paragraph (d).

(3) The appointed person must make a decision and notify it to the appeal parties, with reasons, within 20 working days of expiry of the 20-working day period referred to in sub-paragraph (2)(e) or, if applicable, within 20 working days of the expiry of the 10-working day period referred to in sub-paragraph (6).

(4) The appointment of the person pursuant to sub-paragraph (2)(c) may be undertaken by a person appointed by the Secretary of State for this purpose instead of by the Secretary of State.

(5) If the appointed person considers that further information is necessary to enable consideration of the appeal the appointed person must, as soon as practicable, notify the appeal parties in writing specifying the further information required, the appeal party from whom the information is sought, and the date by which the information is to be submitted.

(6) Any further information required under sub-paragraph (5) is to be provided by the party from whom the information is sought to the appointed person and to other appeal parties by the date specified by the appointed person. Any written representations concerning matters contained in the further information must be submitted to the appointed person, and made available to all appeal parties within 10 working days of that date.

(7) On an appeal under this paragraph, the appointed person must—

(a)allow or dismiss the appeal; or

(b)reverse or vary any part of the decision of the discharging authority (whether the appeal relates to that part of it or not),

and may deal with the application as if it had been made to the appointed person in the first instance.

(8) The appointed person must proceed to a decision on an appeal taking into account only such written representations as have been sent within the prescribed time limits, or other time limits set by the appointed person under this sub-paragraph.

(9) The appointed person must proceed to a decision even though no written representations have been made within the prescribed time limits, or any other time limit set in accordance with sub-paragraph (9).

(10) The decision of the appointed person on an appeal is to be final and binding on the appeal parties, and a court may entertain proceedings for questioning the decision only if the proceedings are brought by a claim for judicial review.

(11) If an approval is given by the appointed person under this Part of this Schedule, it is deemed to be an approval for the purpose of any consent, agreement or approval required under the requirement as if it had been given by the discharging authority. The discharging authority may confirm any determination given by the appointed person in identical form in writing but a failure to give such confirmation (or a failure to give it in identical form) is not to be taken to affect or invalidate the effect of the appointed person's determination.

(12) Except where a direction is given under sub-paragraph (13) requiring the costs of the appointed person to be paid by the discharging authority, the reasonable costs of the appointed person are to be met by the undertaker M5.

(13) On application by the discharging authority or the undertaker, the appointed person may give directions as to the costs of the appeal parties and as to the parties by whom the costs of the appeal are to be paid. In considering whether to make any such direction and the terms on which it is to be made, the appointed person must have regard to the Planning Practice Guidance published by the Department for Communities and Local Government on 6th March 2014 or any circular or guidance which may from time to time replace it.

Marginal Citations

M4The appointment is made at the discretion of the Secretary of State, and such appointment may be made by the Planning Inspectorate on behalf of the Secretary of State.

M5The costs of the appointed person are calculated based on the applicable day rate for a Single Inspector as if he or she were appointed under s78/ s79 of the PA2008. See the National Infrastructure Planning website for more information: https://infrastructure.planninginspectorate.gov.uk/application-process/application-fees/

FeesU.K.

46.—(1) Where an application is made to the discharging authority for consent, agreement or approval in respect of a requirement, other than where the parties have agreed otherwise, the fee that would have been payable had the fee been determined under the Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 2012 M6, is to be paid to that authority.

(2) Any fee paid under this Part of this Schedule must be refunded to the undertaker within 42 days of—

(a)the application being rejected as invalidly made; or

(b)the discharging authority failing to determine the application within the decision period as determined under paragraph (1),

unless within that period the undertaker agrees, in writing, that the fee is to be returned by the discharging authority and credited in respect of a future application.

Marginal Citations

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources