SCHEDULE 12E+WPROTECTIVE PROVISIONS

PART 3E+WFOR THE PROTECTION OF NATIONAL GRID AS ELECTRICITY UNDERTAKER

Protective works to buildingsE+W

22.  The promoter, in the case of the powers conferred by article 22 (protective work to buildings), must exercise those powers so as not to obstruct or render less convenient the access to any apparatus without the written consent of National Grid (such consent not to be unreasonably withheld).E+W

Commencement Information

I1Sch. 12 para. 22 in force at 11.6.2020, see art. 1