Search Legislation

The M42 Junction 6 Development Consent Order 2020

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: Cross Heading: Regulation of powers

 Help about opening options

Alternative versions:

Changes to legislation:

There are currently no known outstanding effects for the The M42 Junction 6 Development Consent Order 2020, Cross Heading: Regulation of powers. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Regulation of powersE+W

36.—(1) The undertaker must before commencing construction of any specified work supply to the company proper and sufficient plans of that work for the reasonable approval of the company’s engineer and the specified work must not be commenced except in accordance with such plans as have been approved in writing by the company’s engineer or settled by arbitration.E+W

(2) The approval of the company’s engineer under sub-paragraph (1) must not be unreasonably withheld or delayed, and may be made subject to such conditions as are reasonably necessary to mitigate the impact of the specified works on the construction, commissioning, maintenance, operation or safety of the HS2 works.

(3) Without limiting the scope of sub-paragraph (2), if by the end of the period of 28 days beginning with the date on which plans are supplied to the company under sub-paragraph (1), the company’s engineer has not intimated disapproval of those plans and the grounds of disapproval the undertaker may serve upon the company’s engineer written notice requiring the company’s engineer to intimate approval or disapproval within a further period of 28 days.

(4) If by the end of the period of 28 days beginning with the date upon which the company’s engineer receives notice under sub-paragraph (3), the engineer has not intimated approval or disapproval, the engineer is deemed to have approved the plans as submitted.

Commencement Information

I1Sch. 12 para. 36 in force at 11.6.2020, see art. 1

37.—(1) Any specified work must, when commenced, be constructed—E+W

(a)without unreasonable delay in accordance with the plans approved or deemed to have been approved or settled under paragraph 36 unless otherwise agreed in writing between the company and the undertaker;

(b)under the supervision (where appropriate and if given) and to the reasonable satisfaction of the company’s engineer; and

(c)in such manner as to cause as little damage as is possible to the HS2 land.

(2) If any such damage is caused by the carrying out of, or in consequence of the construction of, a specified work, the company may inspect the damage and either—

(a)direct that the undertaker, regardless of any approval described in paragraph 36(1), make good such damage and pay to the company all reasonable expenses to which the company may be put and compensation for any costs or losses which it may sustain by reason of any such damage; or

(b)except in relation to HS2 land vested in the undertaker, elect to make good such damage itself and recover from the undertaker all reasonable expenses to which the company may be put and compensation for any costs or losses which it may sustain by reason of any such damage.

(3) Nothing in this Part of this Schedule imposes—

(a)any liability on the undertaker with respect to any damage, costs, expenses or loss attributable to the negligence of the company or its servants, contractors or agents; or

(b)any liability on the company with respect to any damage, costs, expenses or loss attributable to the negligence of the undertaker or its servants, contractors or agents.

Commencement Information

I2Sch. 12 para. 37 in force at 11.6.2020, see art. 1

38.  The undertaker must—E+W

(a)at all times afford reasonable facilities to the company’s engineer for access to a specified work during its construction; and

(b)supply the company’s engineer with all such information as the company’s engineer may reasonably require with regard to a specified work or the method of constructing it.

Commencement Information

I3Sch. 12 para. 38 in force at 11.6.2020, see art. 1

39.  The undertaker must repay to the company all fees, costs, charges and expenses reasonably and properly incurred by the company in respect of the approval by the company’s engineer of plans submitted by the undertaker and the supervision by the company’s engineer of the construction of a specified work.E+W

Commencement Information

I4Sch. 12 para. 39 in force at 11.6.2020, see art. 1

40.—(1) Regardless of any provision in this Order or anything shown on the land plans, the undertaker must not permanently or temporarily acquire HS2 land or any rights on, across, under or over HS2 land otherwise than by written agreement with the company.E+W

(2) The undertaker must not exercise the powers conferred by article 23 (authority to survey and investigate the land) in respect of any HS2 land otherwise than by written agreement with the company.

(3) The provisions of this paragraph do not apply to any HS2 land that is vested in the undertaker.

Commencement Information

I5Sch. 12 para. 40 in force at 11.6.2020, see art. 1

Back to top

Options/Help

Print Options

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources