The Cleve Hill Solar Park Order 2020

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening OptionsExpand opening options

Changes over time for: Paragraph 15

 Help about opening options

Alternative versions:

Status:

Point in time view as at 19/06/2020.

Changes to legislation:

There are currently no known outstanding effects for the The Cleve Hill Solar Park Order 2020, Paragraph 15. Help about Changes to Legislation

ArbitrationU.K.

15.  Save for differences or disputes arising under paragraphs 7(2), , 8(1) and any difference or dispute arising between the undertaker and National Grid under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and National Grid, be determined by arbitration in accordance with article 35 (arbitration).

Commencement Information

I1Sch. 7 para. 15 in force at 19.6.2020, see art. 1