PART 4SUPPLEMENTAL POWERS
Discharge of water17.
(1)
Subject to paragraphs (3) and (4) the undertaker may use any watercourse or any public sewer or drain for the drainage of water in connection with the carrying out, maintenance or use of the authorised development and for that purpose may lay down, take up and alter pipes and may, on any land within the Order limits, make openings into, and connections with, the watercourse, public sewer or drain.
(2)
Any dispute arising from the making of connections to or the use of a public sewer or drain by the undertaker under paragraph (1) is to be determined as if it were a dispute under section 106 (right to communicate with public sewers) of the Water Industry Act 1991 M1.
(3)
The undertaker must not discharge any water into any watercourse, public sewer or drain except with the consent of the person to whom it belongs; and such consent may be given subject to such terms and conditions as that person may reasonably impose, but must not be unreasonably withheld.
(4)
The undertaker must not make any opening into any public sewer or drain except—
(a)
in accordance with plans approved by the person to whom the sewer or drain belongs, but such approval must not be unreasonably withheld; and
(b)
where that person has been given the opportunity to supervise the making of the opening.
(5)
The undertaker must not, in carrying out or maintaining works under this article, damage or interfere with the bed or banks of any watercourse forming part of a main river.
(6)
The undertaker must take such steps as are reasonably practicable to secure that any water discharged into a watercourse or public sewer or drain pursuant to this article is free from gravel, soil or other solid substance, oil or matter in suspension.
(7)
Nothing in this article overrides the requirement for an environmental permit under regulation 12 (requirement for an environmental permit) of the Environmental Permitting (England and Wales) Regulations 2016 M2.
(8)
In this article—
(a)
“public sewer or drain” means a sewer or drain which belongs to the Homes and Communities Agency, the Environment Agency, an internal drainage board, a joint planning board, a local authority, a sewerage undertaker or an urban development corporation; and
(b)
other expressions, excluding watercourse, used both in this article and in the Water Resources Act 1991 M3 have the same meaning as in that Act.
(9)
If a person who receives an application for consent under paragraph (3) or approval under paragraph (4)(a) fails to notify the undertaker of a decision within 28 days of receiving an application that person will be deemed to have granted consent or given approval, as the case may be.
Protective work to buildings18.
(1)
Subject to the following provisions of this article, the undertaker may at its own expense carry out such protective works to any building which may be affected by the authorised development as the undertaker considers necessary or expedient.
(2)
Protective works may be carried out—
(a)
at any time before or during the carrying out in the vicinity of the building of any part of the authorised development; or
(b)
after the completion of that part of the authorised development in the vicinity of the building at any time up to the end of the period of 5 years beginning with the day on which that part of the authorised development is first opened for use.
(3)
For the purpose of determining how the functions under this article are to be exercised the undertaker may enter and survey any building falling within paragraph (1) and any land within its curtilage.
(4)
For the purpose of carrying out protective works under this article to a building the undertaker may (subject to paragraphs (5) and (6))—
(a)
enter the building and any land within its curtilage; and
(b)
where the works cannot be carried out reasonably conveniently without entering land which is adjacent to the building but outside its curtilage, enter the adjacent land (but not any building erected on it).
(5)
Before exercising—
(a)
a right under paragraph (1) to carry out protective works to a building;
(b)
a right under paragraph (3) to enter a building and land within its curtilage;
(c)
a right under paragraph (4)(a) to enter a building and land within its curtilage; or
(d)
a right under paragraph (4)(b) to enter land,
the undertaker must, except in the case of emergency, serve on the owners and occupiers of the building or land not less than 14 days' notice of its intention to exercise that right and, in a case falling within sub-paragraph (a) or (c), specifying the protective works proposed to be carried out.
(6)
Where a notice is served under paragraph (5)(a), (c) or (d), the owner or occupier of the building or land concerned may, by serving a counter-notice within the period of 10 days beginning with the day on which the notice was served, require the question whether it is necessary or expedient to carry out the protective works or to enter the building or land to be referred to arbitration under article 43 (arbitration).
(7)
Where the proposed protective works would, but for the provisions of this Order, require consent under section 8 (authorisation of works: listed building consent) of the Planning (Listed Buildings and Conservation Areas) Act 1990 M4 (other than in respect of the buildings identified in Work No.30 of Schedule 1), the undertaker may not serve a notice under paragraph (5(a) until a description of the proposed protective works has been submitted to and approved in writing by the Secretary of State following consultation with—
(a)
the relevant planning authority; and
(b)
Historic England (if Historic England would have been required to be notified of the application for consent under section 8 by a direction given under section 15(5) of that Act) M5.
(8)
The undertaker must compensate the owners and occupiers of any building or land in relation to which rights under this article have been exercised for any loss or damage arising to them by reason of the exercise of those rights.
(9)
Where—
(a)
protective works are carried out under this article to a building; and
(b)
within the period of 5 years beginning with the day on which the part of the authorised development carried out in the vicinity of the building is first opened for use it appears that the protective works are inadequate to protect the building against damage caused by the carrying out or use of that part of the authorised development,
the undertaker must compensate the owners and occupiers of the building for any loss or damage sustained by them.
(10)
Nothing in this article relieves the undertaker from any liability to pay compensation under section 152 M6 (compensation in case where no right to claim in nuisance) of the 2008 Act.
(11)
Any compensation payable under paragraph (8) or (9) is to be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
(12)
In this article “protective works” in relation to a building means—
(a)
underpinning, strengthening and any other works the purpose of which is to prevent damage which may be caused to the building by the carrying out, maintenance or use of the authorised development; and
(b)
any works the purpose of which is to remedy any damage which has been caused to the building by the carrying out, maintenance or use of the authorised development.
Authority to survey and investigate the land19.
(1)
The undertaker may for the purposes of this Order enter on any land shown within the Order limits or which may be affected by the authorised development and—
(a)
survey or investigate the land;
(b)
without limitation to the scope of sub-paragraph (a), make trial holes in such positions on the land as the undertaker thinks fit to investigate the nature of the surface layer and subsoil and remove soil samples;
(c)
without limitation to the scope of sub-paragraph (a), carry out ecological or archaeological investigations on such land; and
(d)
place on, leave on and remove from the land apparatus for use in connection with the survey and investigation of land and making of trial holes.
(2)
No land may be entered or equipment placed or left on or removed from the land under paragraph (1) unless at least 14 days' notice has been served on every owner and occupier of the land.
(3)
Any person entering land under this article on behalf of the undertaker—
(a)
must, if so required, before or after entering the land, produce written evidence of their authority to do so; and
(b)
may take onto the land such vehicles and equipment as are necessary to carry out the survey or investigation or to make the trial holes.
(4)
No trial holes are to be made under this article—
(a)
in land located within a highway boundary without the consent of the highway authority; or
(b)
in a private street without the consent of the street authority,
but such consent must not be unreasonably withheld.
(5)
The undertaker must compensate the owners and occupiers of the land for any loss or damage arising by reason of the exercise of the authority conferred by this article, such compensation to be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
(6)
If either a highway authority or street authority which receives an application for consent fails to notify the undertaker of its decision within 28 days of receiving the application for consent—
(a)
under paragraph (4)(a) in the case of a highway authority; or
(b)
under paragraph (4)(b) in the case of a street authority,
that authority will be deemed to have granted consent.