Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Article 29
Commencement Information
I1Sch. 7 in force at 18.6.2020, see art. 1
(1) Plot Reference Number shown on Land Plans | (2) Purpose for which temporary possession may be taken | (3) Relevant part of the authorised development |
---|---|---|
Land Plans – Sheet 1 | ||
1/1a, 1/1b, 1/1c, 1/1d, 1/1e, 1/1f | Diversion of statutory undertakers' apparatus, telecommunications cable | Work No.3 |
Land Plans – Sheet 2 | ||
2/1a, 2/3a, 2/2a, 2/4b, 2/4a, 2/4c, 2/4d, 2/5b, 2/4h, 2/4g, 2/2b, 2/4j, 2/1b, 2/1h, 2/1i, 2/1g, 2/1j, 2/1b, 2/1c, 2/4e, 2/4f, 2/1d | Diversion of statutory undertakers' apparatus, telecommunications cable | Work No.3 |
2/5a | Construction of a site compound and vehicle recovery site. | Work No.4 |
Land Plans – Sheet 3 | ||
3/1e, 3/1h, 3/1i, 3/1q, 3/1t, 3/1u, 3/1z, 3/1ab, 3/1ad, 3/1ah, 3/1al | Diversion of statutory undertakers' apparatus (BT) along Osbourne Street, Porter Street and across the A63 Hessle Road. | Work No.6 |
3/1c | Construction of St James' Street turning head. | Work No.7 |
3/1c, 3/1bc | Diversion of statutory undertakers' apparatus (KCOM) along Lister Street, Kingston Street and Commercial Road. | Work No.8 |
3/1e, 3/1h, 3/1i, 3/1q, 3/1t, 3/1u, 3/1z, 3/1ab, 3/1am, 3/1ar, 3/1au, 3/1at | Diversion of statutory undertakers' apparatus (BT and KCOM) along Porter Street, Adelaide Street, Amy Johnson Court and Waterhouse Lane. | Work No.11 |
3/3d, 3/3i, 3/3f, 3/3k, 3/3n, 3/3p, 3/3t, 3/7a, 3/1aj, 3/2d | Demolition of the Arco office complex for use as a site compound | Work No.9 |
3/2d | Diversion of statutory undertakers' apparatus (YW) along Waverley Street. | Work No.10 |
3/1s, 3/1y, 3/1aa, 3/1ac, 3/1zb, 3/1za | Demolition of the existing Myton centre, construction of temporary carpark and construction of green space as replacement open space land. | Work No.13 |
3/1ac, 3/1ai, 3/1an, 3/1ao, 3/1ap | Construction of a new turning head at William Street, and the provision of a new area at William Street and Cogan Street. | Work No.17 |
3/5b, 3/5c, 3/5d, 3/5e, 3/5g, 3/5za | Alterations to Kingston Retail Park car park and working room for construction. | Work No.18A and Work No.18B |
3/1as, 3/1au, 3/1at, 3/7e, 3/8a, 3/8b | Improvement of the existing dual carriageway of the A1079 Ferensway to the north of Mytongate Junction and improvements to Commercial Road to the south of Mytongate Junction. | Work No.19 |
3/1bj, 3/1bl, 3/1bq, 3/1bt | Diversion of statutory undertakers' apparatus (KCOM) along Myton Street, Carr Lane and Princes Dock Street. | Work No.25 |
3/1bp | Alterations to Holiday Inn car park, access, internal roads and amendments to the existing drainage arrangements | Work No.26 |
3/10b | Construction of main site compound at Wellington Street | Work No.29 |
3/11a, 3/11b | Work to Castle Building and Earl de Grey public house, including demolition of Earl De Grey public house and rebuilding 3m to the north of existing position. | Work No.30 |
3/1be, 3/1bf, 3/1bg, 3/1zl | Construction of a surface water rising main. | Work No.46 |
Land Plans – Sheet 4 | ||
4/1q, 4/1r, 4/1s, 4/1m, 4/1n, 4/1o, 4/1p, 4/1l, 4/1w 4/x, 4/1y, 4/1z, 4/1aa, 4/1ac | Diversion of statutory undertakers apparatus (KCOM) along Myton Street, Carr Lane and Princes Dock Street. | Work No.25 |
4/1b, 4/1a, 4/1c, 4/1j, 4/1i, 4/1k | Diversion of statutory undertakers apparatus (BT) along Osbourne Street, Porter Street and across the A63 Hessle Road. | Work No.6 |
Land Plans – Sheet 5 | ||
5/2a | Alterations to Holiday Inn car park | Work No.26 |
5/3a, 5/3d | Construction of main site compound at Wellington Street | Work No. 29 |
5/2af | Offsite archaeology works | Work No.32 |
5/2al, 5/2ay, 5/2bg, 5/2bo, 5/2bi, 5/2bq, 5/2bm, 5/2ce | Old Town improvement works | Work No.33 |
5/2aq, 5/2za, 5/2zc, 5/2zd | Construction and improvements to Humber Dock Street. | Work No.34 |
Land Plans – Sheet 6 | ||
6/1a | Construction of material storage compound | Work No.1 |
6/2a | Construction of vehicle recovery compound | Work No.2 |
6/2b | Construction of vehicle recovery compound | Work No.42 |
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: