83. In this Part—
“apparatus” means the cables, structures or other infrastructure owned, occupied or maintained by Orsted or its successor in title within the Hornsea Three Order Land;
“construction” includes execution, placing, altering, replacing, reconstruction, relaying, maintenance, extensions, enlargement and removal; and “construct” and “constructed” must be construed accordingly;
“Crossing Area” means the land within land parcel 21/08 shown on the land plans and described in the book of reference;
“Orsted” means an undertaker with the benefit of all or part of the Hornsea Three Order for the time being;
“Hornsea Three Order” means any development consent order made by the Secretary of State in relation to Hornsea Three Offshore Wind Farm following the application of 14 May;
“Hornsea Three Order land” means Order land as defined in the Hornsea Three Order;
“plans” includes sections, drawings, specifications, designs, design data, software, soil reports, calculations, descriptions (including descriptions of methods of construction), staging proposals, programmes and details of the extent, timing and duration of any proposed occupation of the Hornsea Three Order land;
“proposed Hornsea Three Cable Corridor” means the proposed location for any electrical circuit(s) and construction compound(s) permitted by the Hornsea Three Order within the Hornsea Three Order land;
“specified works” means so much of any works or operations authorised by this Order (or authorised by any planning permission intended to operate in conjunction with this Order) as is—
(a)
within the Crossing Area;
(b)
in, on, under, over or within 25 metres of the proposed Hornsea Three Cable Corridor or any apparatus; or
(c)
may in any way adversely affect any apparatus.