
Print Options
PrintThe Whole
Instrument
PrintThe Whole
Part
PrintThis
Section
only
Status:
This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
Limits of deviation
6.—(1) In carrying out the authorised development the undertaker may—
(a)deviate laterally from the lines or situations of the authorised development shown on the works plans to the extent of the limits of deviation shown on those plans; and
(b)deviate vertically from the levels of the authorised development shown on the engineering drawings and sections to a maximum of 0.50 metres upwards or 0.50 metres downwards,
except that these maximum limits of vertical deviation do not apply where it is demonstrated by the undertaker to the Secretary of State’s satisfaction and the Secretary of State, following consultation with the relevant planning authority, certifies accordingly that a deviation in excess of these limits would not give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement.
(2) Part 2 (procedure for discharge of requirements) of Schedule 2 (requirements) shall apply to an application to the Secretary of State for certification under paragraph (1) as though it were an approval required by a requirement under that Schedule.
Back to top