2020 No. 807
The Progress Power (Gas Fired Power Station) (Amendment) Order 2020
Made
Coming into force
An Application has been made, under paragraph 2 of Schedule 6 to the Planning Act 20081, to the Secretary of State in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 20112 for non-material changes to the Progress Power (Gas Fired Power Station) Order 20153.
The Secretary of State, having considered the application, the responses to the publicity and consultation required by regulations 6 and 7 of the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011, has decided to make the changes on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.
Accordingly, the Secretary of State, in exercise of the powers conferred by paragraphs 2(1) and (9) of Schedule 6 to the Planning Act 2008, makes the following Order—