- Latest available (Revised)
- Point in Time (17/05/2021)
- Original (As made)
Version Superseded: 01/02/2023
Point in time view as at 17/05/2021. This version of this provision has been superseded.
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
There are currently no known outstanding effects for the The Immingham Open Cycle Gas Turbine Order 2020, Section 2.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
2.—(1) In this Order—
“the 1961 Act” means the Land Compensation Act 1961 M1;
“the 1965 Act” means the Compulsory Purchase Act 1965 M2;
“the 1980 Act” means the Highways Act 1980 M3;
“the 1981 Act” means the Compulsory Purchase (Vesting Declarations) Act 1981 M4;
“the 1984 Act” means the Road Traffic Regulation Act 1984 M5;
“the 1990 Act” means the Town and Country Planning Act 1990 M6;
“the 1991 Act” means the New Roads and Street Works Act 1991 M7;
“the 2008 Act” means the Planning Act 2008 M8;
“access and rights of way plans” means the plans which are certified as the access and rights of way plans by the Secretary of State under article 39 [F1(certification of plans etc.) for] the purposes of this Order;
“address” includes any number or address used for the purposes of electronic transmission;
“apparatus” has the same meaning as in Part 3 (street works in England and Wales) of the 1991 Act and further includes pipelines (and parts of them), aerial markers, cathodic protection test posts, field boundary markers, transformer rectifier kiosks, electricity cables, telecommunications equipment and electricity cabinets;
“Anglian Water” means Anglian Water Services Limited (company number 2366656) whose registered address is Lancaster House Lancaster Way, Ermine Business Park, Huntingdon, Cambridge, United Kingdom PE29 6XU;
“authorised development” means the development described in Schedule 1 (authorised development) and any other development authorised by this Order within the meaning of section 32 (meaning of “development”) of the 2008 Act;
“book of reference” means the document of that description set out in Schedule 11 [F1(documents and plans to be certified)] certified by the Secretary of State as the book of reference under [F1article 39 (certification of plans etc.)] for the purposes of this Order;
“building” includes any structure or erection or any part of a building, structure or erection;
“carriageway” has the same meaning as in the 1980 Act;
“commence” means to carry out any material operation, as defined in section 155 (when development begins) of the 2008 Act, comprised in or carried out for the purposes of the authorised development and the words “commencement” and “commenced” and cognate expressions are to be construed accordingly;
“commissioning” means the process of testing all systems and components of the authorised development (which are installed or in relation to which installation is nearly complete) in order to ensure that they, and the authorised development as a whole, function in accordance with the plant design specifications and the undertaker's operational and safety requirements;
“commitments register” means the plans which are certified as the access and rights of way plans by the Secretary of State under article 39 [F1(certification of plans etc.) for] the purposes of this Order;
“date of completion of construction” means the date on which the construction of the authorised development is complete including rectification of any construction defects, landscaping and reinstatement works;
“date of final commissioning” means the date on which the authorised development commences operation by generating power on a commercial basis, but excluding the generation of power during commissioning;
“electronic transmission” means a communication transmitted—
by means of an electronic communications network; or
by other means provided it is in electronic form;
“emergency” means a situation where, if the relevant action is not taken, there will be adverse health, safety, security or environmental consequences that, in the reasonable opinion of the undertaker, would outweigh the adverse effects to the public (whether individuals, classes or generally as the case may be) of taking that action;
“the environmental statement” means the statement certified as the environmental statement by the Secretary of State under article 39 (certification of plans etc.) for the purposes of this Order;
“flood risk assessment” means the document certified as the flood risk assessment by the Secretary of State under article 39 (certification of plans etc.) for the purposes of this Order;
“footpath” and “footway” have the same meaning as in the 1980 Act;
“framework biodiversity enhancement and management plan” means the plan which is certified as the framework biodiversity enhancement and management plan by the Secretary of State under article 39 (certification of plans etc.) for the purposes of this [F2Order] ;
“framework construction environmental management plan” means the plan which is certified as the framework construction environmental management plan by the Secretary of State under article 39 (certification of plans etc.) for the purposes of this Order;
“framework construction traffic management plan” means the plan which is certified as the framework construction traffic management plan by the Secretary of State under article 39 (certification of plans etc.) for the purposes of this Order;
“framework construction worker travel plan” means the plan which is certified as the framework construction worker travel plan by the Secretary of State under article 39 (certification of plans etc.) for the purposes of this Order;
“framework written scheme of investigation” means the documents which are certified as the framework written scheme of investigation documents by the Secretary of State under article 39 (certification of plans etc.) for the purposes of this Order;
“highway” and “highway authority” have the same meaning as in the 1980 Act;
“indicative lighting strategy” means the documents which are certified as the indicative lighting strategy documents by the Secretary of State under article 39 (certification of plans etc.) for the purposes of this Order;
“land plans” means the plans which are certified as the land plans by the Secretary of State under article 39 (certification of plans etc.) for the purposes of this Order;
“limits of deviation” means in respect of numbered works 1, 2, 3, 4, 5 and 6 the outer limits of the corresponding numbered area shown on the works plan;
“maintain” includes, inspect, repair, adjust, alter, remove, refurbish, reconstruct, replace and improve any part, but not the whole of, the authorised development provided that such activities are not likely to give rise to any significant adverse effects that have not been assessed in the environmental statement and “maintenance” and “maintaining” are to be construed accordingly;
“National Grid” means National Grid Electricity Transmission plc (Company Registration Number 02366977) whose registered office is at 1 to 3 Strand, London, WE2N 5EH and/or National Grid Gas plc (Company Registration Number 02006000) whose registered office is at 1 to 3 Strand, London WC2N 5EH as the context requires;
“Network Rail” means Network Rail Infrastructure Limited (Company Registration Number 02904587) whose registered office is at 1 Eversholt Street, London, NW1 2DN;
“Order land” means the land which is required for, or is required to facilitate, or is incidental to, or is affected by, the authorised development shown coloured pink, blue and yellow on the land plans and described in the book of reference;
“Order limits” means the Order limits shown on the works plans;
“owner”, in relation to land, has the same meaning as in section 7 (interpretation) of the Acquisition of Land Act 1981 M9;
“relevant planning authority” means the local planning authority for the land in question, being North Lincolnshire Council, or any successor to it as planning authority;
“requirements” means those matters set out in Schedule 2 (requirements) to this Order;
“statutory undertaker” means any person falling within section 127(8) (statutory undertakers' land) of the 2008 Act;
“statement to inform appropriate assessment” means statement to inform appropriate assessment which are certified as by the Secretary of State under article 39 (certification of plans etc.) for the purposes of this Order;
“street” means a street within the meaning of section 48 (streets, street works and undertakers) of the 1991 Act, together with land on the verge of a street or between two carriageways, and includes any footpath and “street” includes any part of a street;
“street authority”, in relation to a street, has the same meaning as in Part 3 (street works in England and Wales) of the 1991 Act;
“traffic authority” has the same meaning as in section 121A (traffic authorities) of the 1984 Act;
“tribunal” means the Lands Chamber of the Upper Tribunal;
“undertaker” means VPI Immingham B Limited or the person who for the time being has the benefit of this Order in accordance with articles 6 (benefit of this Order) and 7 (consent to transfer benefit of the Order);
“VPI Immingham B Limited” means VPI Immingham B Limited (Company number 10630563) whose registered office is at 4th Floor, Nova South, 160 Victoria Street, London, England, SW1E 5LB;
“watercourse” includes all rivers, streams, creeks, ditches, drains, canals, cuts, culverts, dykes, sluices, sewers and passages through which water flows except a public sewer or drain; and
“works plans” means the plans of that description set out in Schedule 11.
(2) References in this Order to rights over land include references to rights to do or to place and maintain anything in, on or under land or in the airspace above its surface and to any trusts or incidents (including restrictive covenants) to which the land is subject and references in this Order to the creation or acquisition of new rights include the imposition of restrictive covenants which interfere with interests or rights of another and are for the benefit of land which is acquired under this Order or is otherwise comprised in the Order.
(3) All distances, directions and lengths referred to in this Order are approximate and distances between lines and/or points on a numbered work comprised in the authorised development and shown on the works plan and access and rights of way plan are to be taken to be measured along that work.
(4) All areas described in square metres in the book of reference are approximate.
(5) References in this Order to numbered works are references to the works comprising the authorised development as numbered in Schedule 1 (authorised development) and shown on the works plans.
(6) The expression “includes” is to be construed without limitation.
(7) References in this Order to plots are references to the plots shown on the land plans and described in the book of reference.
Textual Amendments
F1Words in art. 2 substituted (17.5.2021) by The Immingham Open Cycle Gas Turbine (Correction) Order 2021 (S.I. 2021/581), art. 1, Sch.
F2Word in art. 2 substituted (17.5.2021) by The Immingham Open Cycle Gas Turbine (Correction) Order 2021 (S.I. 2021/581), art. 1, Sch.
Commencement Information
I1Art. 2 in force at 1.9.2020, see art. 1
Marginal Citations
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: