Search Legislation

The Immingham Open Cycle Gas Turbine Order 2020

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: PART 5

 Help about opening options

Changes to legislation:

There are currently no known outstanding effects for the The Immingham Open Cycle Gas Turbine Order 2020, PART 5 . Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

PART 5 E+WPOWERS OF ACQUISITION

Compulsory acquisition of landE+W

18.—(1) The undertaker may acquire compulsorily so much of the Order land as is required for the authorised development, or to facilitate it, or as is incidental to it.

(2) This article is subject to article 21 (compulsory acquisition of rights etc.) and article 27 (temporary use of land for carrying out the authorised development).

Commencement Information

I1Art. 18 in force at 1.9.2020, see art. 1

Power to override easements and other rightsE+W

19.—(1) The carrying out or use of the authorised development and the doing of anything else authorised by this Order is authorised for the purpose specified in section 158(2) (nuisance: statutory authority) of the 2008 Act, notwithstanding that it involves—

(a)an interference with an interest or right to which this article applies; or

(b)a breach of a restriction as to use of land arising by virtue of contract.

(2) The undertaker must pay compensation to any person whose land is injuriously affected by—

(a)an interference with an interest or right to which this article applies; or

(b)a breach of a restriction as to use of land arising by virtue of contract,

caused by the carrying out or use of the authorised development and the operation of section 158 (benefit of order granting development consent) of the 2008 Act.

(3) The interests and rights to which this article applies are any easement, liberty, privilege, right or advantage annexed to land and adversely affecting other land, including any natural right to support and include restrictions as to the use of land arising by virtue of a contract.

(4) Section 10(2) (further provision as to compensation for injurious affection) of the 1965 Act applies to paragraph (2) by virtue of section 152(5) (compensation in case where no right to claim in nuisance) of the 2008 Act.

(5) Any rule or principle applied to the construction of section 10 of the 1965 Act must be applied to the construction of paragraph (2) (with any necessary modifications).

Commencement Information

I2Art. 19 in force at 1.9.2020, see art. 1

Time limit for exercise of authority to acquire land compulsorilyE+W

20.—(1) After the end of the period of 5 years beginning on the day on which this Order is made—

(a)no notice to treat is to be served under Part 1 of the 1965 Act; and

(b)no declaration is to be executed under section 4 (execution of declaration) of [F1the 1981 Act as applied by article 23] (application of the 1981 Act).

(2) The authority conferred by article 27 (temporary use of land for carrying out the authorised development) ceases at the end of the period referred to in paragraph (1), save that nothing in this paragraph prevents the undertaker remaining in possession of land after the end of that period, if the land was entered and possession was taken before the end of that period.

Textual Amendments

Commencement Information

I3Art. 20 in force at 1.9.2020, see art. 1

Compulsory acquisition of rights etc.E+W

21.—(1) Subject to paragraph (2), the undertaker may acquire such rights over the Order land or impose such restrictive covenants affecting the Order land as may be required for any purpose for which that land may be acquired under article 18 (compulsory acquisition of land), by creating them as well as acquiring rights already in existence.

(2) In respect of such parts of the Order land that are shown edged red and shaded blue on the land plans, the undertaker may acquire compulsorily the existing rights over land and create and acquire compulsorily the new class of rights and impose the restrictions as described in Table 6 of Schedule 6 (land in which only new rights etc. may be acquired).

(3) Subject to section 8 (provisions as to divided land) and Schedule 2A (counter-notice requiring purchase of land) of the 1965 Act (as substituted by paragraph 5(8) of Schedule 7 (modification of compensation and compulsory purchase enactments for the creation of new rights and [F2imposition of new restrictive covenants)], where the undertaker creates or acquires a right over land or imposes a restrictive covenant under paragraph (1) or (2), the undertaker is not to be required to acquire a greater interest in that land.

(4) Schedule 7 (modification of compensation and compulsory purchase enactments for creation of new rights and [F3imposition of new restrictive covenants)] has effect for the purpose of modifying the enactments relating to compensation and the provisions of the 1965 Act in their application in relation to the compulsory acquisition under this article of a right over land by the creation of a new right or the imposition of a restrictive covenant .

(5) In any case where the acquisition of new rights or imposition of a restriction under paragraph (1) or (2) is required for the purpose of diverting, replacing or protecting apparatus of a statutory undertaker, the undertaker may, with the consent of the Secretary of State, transfer the power to acquire such rights to the statutory undertaker in question.

(6) The exercise by a statutory undertaker of any power in accordance with a transfer under paragraph (5) is subject to the same restrictions, liabilities and obligations as would apply under this Order if that power were exercised by the undertaker.

(7) Subject to the modifications set out in Schedule 7 (modification of compensation and compulsory purchase enactments for creation of new rights and imposition of new restrictive covenants) the enactments for the time being in force with respect to compensation for the compulsory purchase of land are to apply in the case of a compulsory acquisition under this Order in respect of a right by the creation of a new right or imposition of a restriction as they apply to the compulsory purchase of land and interests in land.

Textual Amendments

Commencement Information

I4Art. 21 in force at 1.9.2020, see art. 1

Private rightsE+W

22.—(1) Subject to the provisions of this article, all private rights and restrictions over land subject to compulsory acquisition under this Order are extinguished—

(a)as from the date of acquisition of the land by the undertaker, whether compulsorily or by agreement; or

(b)on the date of entry on the land by the undertaker under section 11(1) (powers of entry) of the 1965 Act,

whichever is the earliest.

(2) Subject to the provisions of this article, all private rights and restrictions over land subject to the compulsory acquisition of rights or imposition of restrictions under this Order are suspended and unenforceable or, where so notified by the undertaker, extinguished in so far as in either case their continuance would be inconsistent with the exercise of the right—

(a)as from the date of acquisition of the right by the undertaker, whether compulsorily or by agreement; or

(b)on the date of entry on the land by the undertaker under section 11(1) (powers of entry) of the 1965 Act in pursuance of the right,

whichever is the earliest.

(3) Subject to the provisions of this article, all private rights over any part of the Order land that is owned by, vested in or acquired by the undertaker are extinguished on commencement of any activity authorised by this Order which interferes with or breaches those rights and where the undertaker gives notice of such extinguishment.

(4) Subject to the provisions of this article, all private rights or restrictions over land of which the undertaker takes temporary possession under this Order are suspended and unenforceable for as long as the undertaker remains in lawful possession of the land and so far as their continuance would be inconsistent with the exercise of the temporary possession of that land.

(5) Any person who suffers loss by the extinguishment or suspension of any private right or restriction under this Order is entitled to compensation to be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(6) This article does not apply in relation to any right to which section 138 (extinguishment of rights, and removal of apparatus, of statutory undertakers etc.) of the 2008 Act or article 29 (statutory undertakers) applies.

(7) Paragraphs (1) to (4) have effect subject to—

(a)any notice given by the undertaker before—

(i)the completion of the acquisition of the land or the creation and acquisition of rights or the imposition of restrictions over land;

(ii)the undertaker's appropriation of it;

(iii)the undertaker's entry onto it; or

(iv)the undertaker's taking temporary possession of it,

that any or all of those paragraphs are not to apply to any right specified in the notice; and

(b)any agreement made at any time between the undertaker and the person in or to whom the right or restriction in question is vested, belongs or benefits.

(8) If any such agreement as is referred to in paragraph (7)(b)—

(a)is made with a person in or to whom the right is vested or belongs; and

(b)is expressed to have effect also for the benefit of those deriving title from or under that person,

it is effective in respect of the persons so deriving title, whether the title was derived before or after the making of the agreement.

(9) References in this article to private rights over land include any right of way, trust, incident, easement, liberty, privilege, restrictions right or advantage annexed to land and adversely affecting other land, including any natural right to support and include restrictions as to the user of land arising by virtue of a contract, agreement or undertaking having that effect.

Commencement Information

I5Art. 22 in force at 1.9.2020, see art. 1

Application of the 1981 ActE+W

23.—(1) The 1981 Act applies as if this Order were a compulsory purchase order.

(2) [F4The 1981 Act] , as applied by paragraph (1), has effect with the following modifications.

(3) In section 1 (application of Act) for subsection 2 there is substituted—

(2) This section applies to any Minister, any local or other public authority or any other body or person authorised to acquire land by means of a compulsory purchase order..

(4) In section 5(2) (earliest date for execution of declaration), omit the words from “, and this subsection” to the end.

(5) Omit section 5A (time limit for general vesting declaration).

(6) In section 5B(1) (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 (application to High Court in respect of compulsory purchase order), the three year period mentioned in section 5A” substitute “ section 118 of the 2008 Act (legal challenges relating to applications for orders granting development consent), the five year period mentioned in article 20 (time limit for exercise of authority to acquire land compulsorily) of the Immingham Open Cycle Gas Turbine Order 2020 ”.

(7) In section 6 (notices after execution of declaration), in subsection (1)(b) for “section 15 of, or paragraph 6 of Schedule 1 to, the Acquisition of Land Act 1981” substitute “ section 134 (notice of authorisation of compulsory acquisition) of the Planning Act 2008 ”.

(8) In section 7 (constructive notice to treat), in subsection (1)(a), omit “(as modified by section 4 of the Acquisition of Land Act 1981)”.

(9) In Schedule A1 (counter-notice requiring purchase of land not in general vesting declaration), for paragraph 1(2) substitute—

(2) But see article 24(3) (acquisition of subsoil only) of the Immingham Open Cycle Gas Turbine Order 2020, which excludes the acquisition of subsoil only from this Schedule.

(10) References to the 1965 Act in [F5the 1981 Act] must be construed as references to that Act as applied by section 125 (application of compulsory acquisition provisions) of the 2008 Act (as modified by article 25 (modification of Part 1 of the 1965 Act)) to the compulsory acquisition of land under this Order.

Textual Amendments

Commencement Information

I6Art. 23 in force at 1.9.2020, see art. 1

Acquisition of subsoil onlyE+W

24.—(1) The undertaker may acquire compulsorily so much of, or such rights in, the subsoil of the land referred to in paragraph (1) of article 18 (compulsory acquisition of land) and paragraphs (1) and (2) of article 21 (compulsory acquisition of rights etc.) as may be required for any purpose for which that land or rights or restrictions over that land may be created and acquired or imposed under that provision instead of acquiring the whole of the land.

(2) Where the undertaker acquires any part of, or rights in, the subsoil of land under paragraph (1), the undertaker is not to be required to acquire an interest in any other part of the land.

(3) The following do not apply in connection with the exercise of the power under paragraph (1) in relation to subsoil only—

(a)Schedule 2A (counter-notice requiring purchase of land not in notice to treat) to the 1965 Act;

(b)Schedule A1 (counter-notice requiring purchase of land not in general vesting declaration) to the 1981 Act; and

(c)section 153(4A) (reference of objection to Upper Tribunal: general) of the 1990 Act.

(4) Paragraphs (2) and (3) do not apply where the undertaker acquires a cellar, vault, arch or other construction forming part of a house, building or manufactory.

Commencement Information

I7Art. 24 in force at 1.9.2020, see art. 1

Modification of Part 1 of the 1965 ActE+W

25.—(1) Part 1 (compulsory purchase under Acquisition of Land Act 1946) of the 1965 Act, as applied to this Order by section 125 (application of compulsory acquisition provisions) of the 2008 Act, is modified as follows.

(2) In section 4A(1) (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 (application to High Court in respect of compulsory purchase order), the three year period mentioned in section 4” substitute “ section 118 of the Planning Act 2008 (legal challenges relating to applications for orders granting development consent), the five year period mentioned in article 20 (time limit for exercise of authority to acquire land compulsorily) of the Immingham Open Cycle Gas Turbine Order 2020 ”.

(3) In section 11A (powers of entry: further notice of entry)—

(a)in subsection (1)(a), after “land” insert “ under that provision ”; and

(b)in subsection (2), after “land” insert “ under that provision ”.

(4) In section 22(2) (interests omitted from purchase), for “section 4 of this Act” substitute “ article 20 (time limit for exercise of authority to acquire land compulsorily) of the Immingham Open Cycle Gas Turbine Order 2020 ”.

(5) In Schedule 2A (counter-notice requiring purchase of land not in notice to treat)—

(a)for paragraphs 1(2) and 14(2) substitute—

(2) But see article 24(3)(acquisition of subsoil only) of the Immingham Open Cycle Gas Turbine Order 2020, which excludes the acquisition of subsoil only from this Schedule; and

(b)after paragraph 29, insert—

PART 4 E+WINTERPRETATION

30.  In this Schedule, references to entering on and taking possession of land do not include doing so under article 27 (temporary use of land for carrying out the authorised development) or article 28 (temporary use of land for maintaining the authorised development) of the Immingham Open Cycle Gas Turbine Order 2020..

Commencement Information

I8Art. 25 in force at 1.9.2020, see art. 1

Rights under or over streetsE+W

26.—(1) The undertaker may enter upon and appropriate so much of the subsoil of, or airspace over, any street within the Order land as may be required for the purposes of the authorised development and may use the subsoil or airspace for those purposes or any other purpose ancillary to the authorised development.

(2) Subject to paragraph (3), the undertaker may exercise any power conferred by paragraph (1) in relation to a street without being required to acquire any part of the street or any easement or right in the street.

(3) Paragraph (2) does not apply in relation to—

(a)any subway or underground building; or

(b)any cellar, vault, arch or other construction in, on or under a street which forms part of a building fronting onto the street.

(4) Subject to paragraph (5) any person who is an owner or occupier of land in respect of which the power of appropriation conferred by paragraph (1) is exercised without the undertaker acquiring any part of that person's interest in the land, and who suffers loss by the exercise of that power, is to be entitled to compensation to be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(5) Compensation is not payable under paragraph (4) to any person who is an undertaker to whom section 85 (sharing cost of necessary measures) of the 1991 Act applies in respect of measures of which the allowable costs are to be borne in accordance with that section.

Commencement Information

I9Art. 26 in force at 1.9.2020, see art. 1

Temporary use of land for carrying out the authorised developmentE+W

27.—(1) The undertaker may, in connection with the carrying out of the authorised development—

(a)enter on and take possession of—

(i)so much of the land specified in column (1) of Schedule 8 (land of which temporary possession may be taken) for the purpose specified in relation to that land in column (2) of that Schedule;

(ii)any other part of the Order land in respect of which no notice of entry has been served under section 11 (powers of entry) of the 1965 Act and no declaration has been made under section 4 (execution of declaration) of the 1981 Act;

(b)remove any buildings, fences, debris and vegetation from that land;

(c)construct temporary works (including the provision of means of access) and buildings on that land;

(d)construct any works specified in relation to that land in column (2) of Schedule 8; and

(e)carry out or construct any other mitigation works.

(2) Before taking temporary possession of land for a period of time by virtue of sub-paragraph (1) the undertaker must give a notice of intended entry to each of the owners and occupiers of the land, so far as known to the undertaker after making diligent inquiry.

(3) The notice in paragraph (2) must specify—

(a)the period after the end of which the undertaker may take temporary possession of the land provided that such period must not end earlier than the end of the period of three months beginning with the day on which the notice is given;

(b)subject to paragraph (4) the period for which the undertaker is to take temporary possession of the land,

provided that such periods may be varied from time to time by agreement between the undertaker and the owner or occupier.

(4) The undertaker may not, without the agreement of the owners of the land, remain in possession of any land under this article—

(a)in the case of land specified in paragraph (1)(a)(i), after the end of the period of one year beginning with the date of final commissioning of the authorised development; or

(b)in the case of land referred to in paragraph (1)(a)(ii), after the end of the period of one year beginning with the date of final commissioning of the authorised development unless the undertaker has, before the end of that period, served notice of entry under section 11 of the 1965 Act or made a declaration under section 4 of [F6the 1981 Act or] has otherwise acquired the land subject to temporary possession.

(5) Unless the undertaker has served notice of entry under section 11 of the 1965 Act or made a declaration under section 4 of the 1981 Act or has otherwise acquired the land subject to temporary possession, the undertaker must, before giving up possession of land of which temporary possession has been taken under this article, remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land; but the undertaker is not to be required to replace a building or any debris removed under this article.

(6) The undertaker must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.

(7) Any dispute as to a person's entitlement to compensation under paragraph (6), or as to the amount of the compensation, is to be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(8) Nothing in this article affects any liability to pay compensation under section 152 of the 2008 Act (compensation in case where no right to claim in nuisance) or under any other enactment in respect of loss or damage arising from the carrying out of the authorised development, other than loss or damage for which compensation is payable under paragraph (6).

(9) The undertaker must not compulsorily acquire under this Order the land referred to in paragraph (1)(a)(i).

(10) Nothing in this article precludes the undertaker from—

(a)creating and acquiring new rights or imposing restrictions over any part of the Order land identified in article 21 (compulsory acquisition of rights etc.); or

(b)acquiring any right in the subsoil of any part of the Order land identified in part 1 of the book of reference under article 24 (acquisition of subsoil only) or article 26 (rights under or over streets).

(11) Where the undertaker takes possession of land under this article, the undertaker is not required to acquire the land or any interest in it.

(12) Section 13 (refusal to give possession to acquiring authority) of the 1965 Act applies to the temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.

(13) Nothing in this article prevents the taking of temporary possession more than once in relation to any land specified in Schedule 8.

(14) The provisions of the Neighbourhood Planning Act 2017 M1 do not apply insofar as they relate to temporary possession of land under this article in connection with the carrying out of the authorised development and other development or works necessary for the authorised development within the Order land.

Textual Amendments

Commencement Information

I10Art. 27 in force at 1.9.2020, see art. 1

Marginal Citations

Temporary use of land for maintaining the authorised developmentE+W

28.—(1) Subject to paragraph (2), at any time during the maintenance period relating to any part of the authorised development, the undertaker may—

(a)enter on and take temporary possession of any of the Order land if such possession is reasonably required for the purpose of maintaining the authorised development;

(b)enter on any of the Order land for the purpose of gaining such access as is reasonably required for the purpose of maintaining the authorised development; and

(c)construct such temporary works (including the provision of means of access) and buildings on the land as may be reasonably necessary for that purpose.

(2) Paragraph (1) does not authorise the undertaker to take temporary possession of—

(a)any house or garden belonging to a house; or

(b)any building (other than a house) if it is for the time being occupied.

(3) Before taking temporary possession of land for a period of time by virtue of paragraph (1) the undertaker must give notice of intended entry to each of the owners and occupiers of the land, so far as known to the undertaker after making diligent inquiry.

(4) The notice in paragraph (3) must specify—

(a)the period after the end of which the undertaker may take temporary possession of the land provided that such period must not end earlier than the end of the period of three months beginning with the day on which the notice is given; and

(b)subject to sub-paragraph (5) the period for which the undertaker is to take temporary possession of the land,

provided that such periods may be varied from time to time by agreement between the undertaker and the owner or occupier.

(5) The undertaker may only remain in possession of land under this article for so long as may be reasonably necessary to carry out the maintenance of the part of the authorised development for which possession of the land was taken.

(6) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.

(7) The undertaker must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.

(8) Any dispute as to a person's entitlement to compensation under paragraph (7), or as to the amount of the compensation, is to be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(9) Nothing in this article affects any liability to pay compensation under section 152 of the 2008 Act (further provisions as to compensation for injurious affection) or under any other enactment in respect of loss or damage arising from the maintenance of the authorised development, other than loss or damage for which compensation is payable under paragraph (7).

(10) Where the undertaker takes possession of land under this article, the undertaker is not required to acquire the land or any interest in it.

(11) Section 13 (refusal to give possession to acquiring authority) of the 1965 Act applies to the temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.

(12) In this article “the maintenance period” means the period of one year beginning with the date of final commissioning.

(13) The provisions of the Neighbourhood Planning Act 2017 M2 do not apply insofar as they relate to temporary possession of land under this article in connection with the maintenance of the authorised development and other development necessary for the authorised development within the Order land.

Commencement Information

I11Art. 28 in force at 1.9.2020, see art. 1

Marginal Citations

Statutory undertakersE+W

29.  Subject to the provisions of Schedule 9 (protective provisions), the undertaker may—

(a)acquire compulsorily the land belonging to statutory undertakers within the Order land;

(b)extinguish or suspend the rights of or restrictions for the benefit of, and remove or reposition the apparatus belonging to, statutory undertakers on, under, over or within the Order land; and

(c)create and acquire compulsorily rights or impose restrictions over any Order land belonging to statutory undertakers.

Commencement Information

I12Art. 29 in force at 1.9.2020, see art. 1

Apparatus and rights of statutory undertakers in streetsE+W

30.  Where a street is altered or diverted or its use is temporarily prohibited or restricted under article 8 (power to alter layout etc. of streets), article 9 (street works), article 10 (construction and maintenance of new or altered means of access) or article 11 (temporary prohibition or restriction of use of streets) any statutory undertaker whose apparatus is under, in, on, along or across the street is to have the same powers and rights in respect of that apparatus, subject to Schedule 9 (protective provisions), as if this Order had not been made.

Commencement Information

I13Art. 30 in force at 1.9.2020, see art. 1

Recovery of costs of new connectionsE+W

31.—(1) Where any apparatus of a public utility undertaker or of a public communications provider is removed under article 29 (statutory undertakers) any person who is the owner or occupier of premises to which a supply was given from that apparatus is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of effecting a connection between the premises and any other apparatus from which a supply is given.

(2) Paragraph (1) does not apply in the case of the removal of a public sewer but where such a sewer is removed under article 29 any person who is—

(a)the owner or occupier of premises the drains of which communicated with the sewer; or

(b)the owner of a private sewer which communicated with that sewer,

is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of making the drain or sewer belonging to that person communicate with any other public sewer or with a private sewerage disposal plant.

(3) This article does not have effect in relation to apparatus to which article 30 (apparatus and rights of statutory undertakers in streets) or Part 3 (street works in England and Wales) of the 1991 Act applies.

(4) In this article—

public communication provider” has the same meaning as in section 151(1) (interpretation of chapter 1) of the Communications Act 2003 M3; and

public utility undertaker” has the same meaning as in the 1980 Act.

Commencement Information

I14Art. 31 in force at 1.9.2020, see art. 1

Marginal Citations

M32003 c.21. Section 151(1) was amended by paragraphs 90(a)(i), (ii), (iii), 90(b), 90(c) and 90(d) of Schedule 1 to the Electronic Communications and Wireless Telegraphy Regulations S.I. 2011/1210.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources