The Immingham Open Cycle Gas Turbine Order 2020

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: SCHEDULE 2

 Help about opening options

Changes to legislation:

There are currently no known outstanding effects for the The Immingham Open Cycle Gas Turbine Order 2020, SCHEDULE 2. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Article 3

SCHEDULE 2E+WREQUIREMENTS

InterpretationE+W

1.  In this Schedule—

Environment Agency” means the non-departmental public body of that name created by section 1 (the Environment Agency) of the Environment Act 1995 M1;

Highways England” means Highways England Company Limited or such other person who is appointed as the strategic highways company in respect of the A160 Humber Road and the A160/A180 interchange pursuant to section 1 (appointment of strategic highways companies) of the Infrastructure Act 2015 M2;

Historic England” means the Historic Buildings and Monuments Commission for England established by section 32 (establishment of commission) of the National Heritage Act 1983 M3;

lead local flood authority” means the body designated as such, for the area in which the authorised development is located, pursuant to section 6(7) (other definitions) of the Flood and Water Management Act 2010 M4;

Lincolnshire Wildlife Trust” means Lincolnshire Wildlife Trust (registered charity number 218895) of Banovallum House, Lincolnshire, LN9 5HF;

North East Lindsey Internal Drainage Board” means the internal drainage board for the area in which the authorised development is located pursuant to section 1 (internal drainage districts and boards) of the Land Drainage Act 1991 M5;

North Lincolnshire Police” means the police force for the area in which the authorised development is located pursuant to section 1 (police areas) of the Police Act 1996 M6;

part of the authorised development” means any part of Works Nos. 1 to 6; and

permitted preliminary works” means operations consisting of environmental surveys and monitoring, investigations for the purpose of assessing ground conditions, archaeological investigations, receipt and erection of construction plant and equipment, erection of any temporary means of enclosure, the temporary display of site notices or advertisements.

Commencement Information

I1Sch. 2 para. 1 in force at 1.9.2020, see art. 1

Marginal Citations

M61996 c.16 as amended by the Local Government and Public Involvement in Health Act 2007 (c.28) and the Policing and Crime Act 2017 (c.3).

Commencement of the authorised developmentE+W

2.—(1) The authorised development must not be commenced after the expiration of five years from the date this Order comes into force.

(2) The authorised development must not commence unless the undertaker has given the relevant planning authority fourteen days' notice of its intention to commence the authorised development.

Commencement Information

I2Sch. 2 para. 2 in force at 1.9.2020, see art. 1

Notice of commencementE+W

3.  Notice of the intended start of commissioning of the authorised development must be given to the relevant planning authority where practicable prior to such start and in any event within seven days from the date that commissioning is started.

Commencement Information

I3Sch. 2 para. 3 in force at 1.9.2020, see art. 1

Notice of date of final commissioningE+W

4.  Notice of the intended date of final commissioning of the authorised development must be given to the relevant planning authority where practicable prior to such date of final commissioning and in any event within seven days from the date of final commissioning.

Commencement Information

I4Sch. 2 para. 4 in force at 1.9.2020, see art. 1

Detailed designE+W

5.—(1) In relation to any part of the authorised development comprised in Work No. 1 no development of that part may commence, save for the permitted preliminary works, until details of the following for that part have been submitted to and, in respect of sub-paragraph (d) after consultation with the highway authority, approved by the relevant planning authority—

(a)the siting, layout, scale and external appearance, including the colour, materials and surface finishes of all new permanent buildings and structures;

(b)finished floor levels;

(c)hard standings;

(d)the internal vehicular access and circulation roads, loading and unloading, vehicle parking and turning facilities, cycle parking and routes, and pedestrian facilities and routes; and

(e)landscaping

(2) The details submitted pursuant to sub-paragraph (1) must be in accordance with the parameters set out in [F1Schedule 12 (design parameters)] .

(3) No part of the authorised development comprised in Work No. 2 may commence, save for the permitted preliminary works, until details of the following for that part have been submitted to and, after consultation with the highway authority, approved by the relevant planning authority—

(a)construction access;

(b)operational access;

(c)vehicle parking; and

(d)haul routes.

(4) No part of the authorised development comprised in Work No. 3 may commence, save for the permitted preliminary works, until details of the following for that part have been submitted to and, in respect of sub-paragraphs (a), (d) and (e) after consultation with the highway authority, approved by the relevant planning authority—

(a)hard standings, laydown and open storage areas;

(b)contractor compounds and construction staff welfare facilities;

(c)gatehouse;

(d)vehicle parking and cycle storage facilities; and

(e)the internal vehicular access and circulation roads, loading and unloading, vehicle parking and turning facilities, cycle parking and routes, and pedestrian facilities and routes.

(5) No part of the authorised development comprised in Work Nos. 4 and 5, save for the permitted preliminary works, may commence until details of the following for that part have been submitted to and, after consultation with National Grid, approved by the relevant planning authority—

(a)the route and method of installation of the gas pipeline; and

(b)the route and method of electrical connection works comprising overground electrical cables, and control systems and cables.

(6) No part of the authorised development comprised in Work No. 6 may commence, save for the permitted preliminary works, until details of the following for that part have been submitted to and, after consultation with the Environment Agency and Anglian Water, approved by the relevant planning authority—

(a)the route and method of construction of any utilities and services connections including water pipes, connections, pumps, tanks, structures and ancillary equipment; telecommunications cables and equipment; electrical cables, connections and ancillary equipment; and control systems and cables; and

(b)water connection works, comprising underground and overground pipes, plant apparatus, enclosures and structures, and supply cables, transformers and control system cables.

(7) Work Nos. 1, 2, 3, 4, 5 and 6 must be carried out in accordance with the approved details unless otherwise agreed with the relevant planning authority.

Textual Amendments

Commencement Information

I5Sch. 2 para. 5 in force at 1.9.2020, see art. 1

Biodiversity enhancement and management planE+W

6.—(1) No part of the authorised development may commence, save for the permitted preliminary works, until a biodiversity protection plan for that part has been submitted to and, after consultation with Natural England, approved by the relevant planning authority.

(2) The plan submitted and approved pursuant to sub-paragraph (1) must include details of—

(a)measures to protect existing shrub and tree planting that is to be retained; and

(b)biodiversity and habitat impact avoidance.

(3) The plan submitted and approved pursuant to sub-paragraph (1) must be implemented as approved throughout the construction of the authorised development unless otherwise agreed with the relevant planning authority.

(4) Prior to the date of final commissioning a biodiversity enhancement and management plan must be submitted to and approved by the relevant planning authority.

(5) The plan submitted and approved pursuant to sub-paragraph (4) must include details of—

(a)measures to protect existing shrub and tree planting that is to be retained;

(b)measures to enhance biodiversity and habitats;

(c)an implementation timetable; and

(d)biodiversity management and maintenance.

(6) Any shrub or tree planted as part of the approved plan that, within a period of five years after planting, is removed, dies or becomes, in the opinion of the relevant planning authority, seriously damaged or diseased, must be replaced in the first available planting season with a specimen of the same species and size as that originally planted unless otherwise agreed with the relevant planning authority.

(7) The plan submitted and approved pursuant to sub-paragraph (4) must be in accordance with the principles of the framework biodiversity enhancement and management plan.

(8) The plan must be implemented as approved during the operation of the authorised development unless otherwise agreed with the relevant planning authority.

Commencement Information

I6Sch. 2 para. 6 in force at 1.9.2020, see art. 1

External lightingE+W

7.—(1) No part of the authorised development may commence, save for the permitted preliminary works, until a scheme for all external lighting to be installed during construction for that part has been submitted to and approved by the relevant planning authority.

(2) No part of the authorised development may be commissioned until a scheme for all permanent external lighting to be installed has been submitted to and approved by the relevant planning authority.

(3) The schemes submitted and approved pursuant to sub-paragraphs (1) and (2) of this requirement must be in accordance with the indicative lighting strategy and include measures to minimise and otherwise mitigate any artificial light emissions during the construction and operation of the authorised development.

(4) The schemes must be implemented as approved unless otherwise agreed with the relevant planning authority.

Commencement Information

I7Sch. 2 para. 7 in force at 1.9.2020, see art. 1

Highway accessesE+W

8.—(1) No part of the authorised development may commence, save for the permitted preliminary works, until details of the siting, design and layout (including visibility splays and construction specification) of any new or modified means of access between any part of the Order limits and the public highway to be used by vehicular traffic during construction, and the means of reinstating any such means of access after construction has, for that part, been submitted to and, after consultation with the highway authority, approved by the relevant planning authority.

(2) The highway accesses approved pursuant to sub-paragraph (1) must be constructed in accordance with the approved details prior to the start of construction of the relevant part of the authorised development (other than the accesses), and where temporary, reinstated prior to the date of final commissioning, unless otherwise agreed with the relevant planning authority.

(3) Prior to the date of final commissioning details of the siting, design and layout (including visibility splays and construction specification) of any new or modified permanent means of access to a highway to be used by vehicular traffic, must be submitted to and, after consultation with the highway authority, approved by the relevant planning authority.

(4) The highway accesses approved pursuant to sub-paragraph (3) must be constructed in accordance with the details approved unless otherwise agreed with the relevant planning authority.

Commencement Information

I8Sch. 2 para. 8 in force at 1.9.2020, see art. 1

Means of enclosureE+W

9.—(1) No part of the authorised development may commence, save for the permitted preliminary works, until a programme for the removal of all temporary means of enclosure for any construction areas or sites associated with the authorised development has, for that part, been submitted to and approved by the relevant planning authority.

(2) Any construction areas or sites associated with the authorised development must remain securely fenced at all times during construction and commissioning of the authorised development.

(3) Any temporary fencing must be removed by the end of three months beginning with the date of completion of construction of the authorised development (or such other period as the relevant planning authority may approve).

(4) Prior to the date of final commissioning details of any proposed permanent means of enclosure must be submitted to and approved by the relevant planning authority.

(5) Any permanent means of enclosure approved pursuant to sub-paragraph (4) must be completed prior to the date of final commissioning.

(6) The authorised development must be carried out in accordance with the approved details unless otherwise agreed with the relevant planning authority.

(7) In this requirement, “means of enclosure” means fencing, walls or other means of boundary treatment and enclosure.

Commencement Information

I9Sch. 2 para. 9 in force at 1.9.2020, see art. 1

Surface water drainageE+W

10.—(1) No part of the authorised development may commence, save for the permitted preliminary works, until details of the temporary surface water drainage systems, including means of pollution control in accordance with the construction environmental management plan submitted pursuant to requirement 14 and a management and maintenance plan to ensure that the systems remain fully operational throughout the construction of the relevant part of the authorised development have, for that part, been submitted to, and after consultation with the lead local flood authority and North East Lindsey Internal Drainage Board, approved by the relevant planning authority.

(2) The scheme approved pursuant to sub-paragraph (1) must be implemented as approved and maintained throughout the construction of the authorised development unless otherwise agreed with the relevant planning authority.

(3) Details of the permanent surface water drainage systems, including a programme for their implementation, must be submitted to, and after consultation with the Environment Agency, the lead local flood authority, Anglian Water and North East Lindsey Internal Drainage Board, approved by the relevant planning authority prior to the start of construction of any part of those systems.

(4) The details submitted and approved pursuant to sub-paragraphs (1) and (3) of this requirement must be in accordance with the principles set out in chapter 12 (surface water, flood risk and drainage) of the environmental statement and the flood risk assessment.

(5) The scheme approved pursuant to sub-paragraph (3) must be implemented as approved and maintained throughout the operation of the authorised development unless otherwise agreed with the relevant planning authority.

Commencement Information

I10Sch. 2 para. 10 in force at 1.9.2020, see art. 1

Flood risk mitigationE+W

11.—(1) No part of the authorised development may commence, save for the permitted preliminary works, until a scheme for the mitigation of flood risk during construction, has, for that part, been submitted to and approved by the relevant planning authority.

(2) The scheme approved pursuant to sub-paragraph (1) must be implemented as approved and maintained throughout the construction of the authorised development unless otherwise agreed with the relevant planning authority.

(3) No part of the authorised development may commence [F2save for the permitted preliminary works] until a scheme for the mitigation of flood risk during operation has, for that part, been submitted to and, after consultation with the Environment Agency and North East Lindsey Internal Drainage Board, approved by the relevant planning authority.

(4) The schemes submitted and approved pursuant to sub-paragraphs (1) and (3) of this requirement must be in accordance with the principles set out in chapter 12 (surface water, flood risk and drainage) of the environmental statement and the flood risk assessment.

(5) The scheme approved pursuant to sub-paragraph (3) must be implemented as approved and maintained throughout the operation of the authorised development unless otherwise agreed with the relevant planning authority.

(6) The authorised development must not be commissioned until the flood risk mitigation has been implemented and a flood emergency response and contingency plan has been submitted to, and after consultation with North East Lindsey Internal Drainage Board, approved by the relevant planning authority.

(7) The plan approved pursuant to sub-paragraph (6) must be implemented throughout the commissioning and operation of the authorised development unless otherwise agreed with the relevant planning authority.

Textual Amendments

Commencement Information

I11Sch. 2 para. 11 in force at 1.9.2020, see art. 1

Contaminated land and groundwaterE+W

12.—(1) No part of the authorised development may commence, save for geotechnical surveys and other investigations for the purpose of assessing ground conditions, until a scheme to deal with the contamination of land, including groundwater, which is likely to cause significant harm to persons or pollution of controlled waters or the environment, has, for that part, been submitted to and, after consultation with the Environment Agency, approved by the relevant planning authority.

(2) The scheme submitted and approved must be in accordance with the principles set out in chapter 11 (ground conditions and hydrogeology) of the Environmental Statement and with the construction environmental management plan submitted pursuant to requirement 14.

(3) The scheme must include a risk assessment, supported by site investigation data, to identify the extent of any contamination and the remedial measures to be taken to render the land fit for its intended purpose, together with a materials management plan, which sets out long-term measures with respect to any contaminants remaining on the site.

(4) The authorised development, including any remediation, must be carried out in accordance with the approved scheme unless otherwise agreed with the relevant planning authority.

(5) Should any remediation be required a verification report demonstrating the completion of works set out in the approved scheme and the effectiveness of the remediation must be submitted to, and approved, by the relevant planning authority prior to the date of final commissioning. The report must include results of sampling and monitoring carried out in accordance with the approved scheme to demonstrate that the site remediation criteria have been met.

Commencement Information

I12Sch. 2 para. 12 in force at 1.9.2020, see art. 1

ArchaeologyE+W

13.—(1) No part of the authorised development may commence until a written scheme of investigation for that part has been submitted to and, after [F3consultation with Historic England], approved by the relevant planning authority.

(2) The scheme submitted and approved must be in accordance with chapter 13 (cultural heritage) of the environmental statement and the framework written scheme of investigation.

(3) The scheme must identify whether any further archaeological investigations are required and, if investigations are deemed to be required, the nature and extent of the investigations in order to preserve by knowledge or in-situ any archaeological features that are identified.

(4) The scheme must provide details of the measures to be taken to protect, record or preserve any significant archaeological features that may be found.

(5) Any archaeological investigations implemented and measures taken to protect, record or preserve any identified significant archaeological features that may be found must be carried out—

(a)in accordance with the approved scheme; and

(b)by a suitably qualified person or organisation approved by the relevant planning authority unless otherwise agreed with the relevant planning authority.

Textual Amendments

Commencement Information

I13Sch. 2 para. 13 in force at 1.9.2020, see art. 1

Construction environmental management planE+W

14.—(1) No part of the authorised development may commence, save for the permitted preliminary works, until a construction environmental management plan has been submitted to and, after consultation with Natural England, approved by the relevant planning authority.

(2) The plan submitted and approved must be in accordance with the framework construction environmental management plan and incorporate—

(a)a code of construction practice, specifying measures designed to minimise the impacts of construction works;

(b)a scheme for the control of emissions of dust;

(c)a soil management plan;

(d)a sediment control plan;

(e)a scheme for environmental monitoring and reporting during the construction of the authorised development, including measures for undertaking any corrective actions;

(f)a scheme for the notification of any significant construction impacts on local residents and for handling any complaints received from local residents relating to such impacts during the construction of the authorised development; and

(g)a requirement that the detail of the fencing and protection of asset A6 is in accordance with the strategy set out in the framework written scheme of investigation.

(3) All construction works associated with the authorised development must be carried out in accordance with the approved construction environmental management plan unless otherwise agreed with the relevant planning authority.

(4) The plan submitted must include information on the proposed piling methods, their approximate duration and timing, the likely sound power levels, and any necessary management measures or mitigation to ensure, taking into account the information in the statement to inform appropriate assessment, that there will be no adverse impact on any qualifying species of the Humber Estuary Special Protection Area and Ramsar Site.

Commencement Information

I14Sch. 2 para. 14 in force at 1.9.2020, see art. 1

Protection of highway surfacesE+W

15.—(1) No part of the authorised development may commence, save for the permitted preliminary works, until details for undertaking condition surveys of the relevant parts of Rosper Road which are maintainable at the public expense and which are to be used during construction have been submitted to and, after consultation with the highway authority, approved by the relevant planning authority.

(2) The condition surveys must be undertaken in accordance with the approved details and a schedule of repairs required due to use by construction traffic for the authorised development, including a programme for undertaking any such repairs and their inspection, must, following the completion of the post-construction condition surveys, be submitted to, and after consultation with the highway authority, approved by the relevant planning authority.

(3) The schedule of repairs must be carried out as approved unless otherwise agreed with the relevant planning authority.

Commencement Information

I15Sch. 2 para. 15 in force at 1.9.2020, see art. 1

Construction traffic management planE+W

16.—(1) No part of the authorised development may commence, save for the permitted preliminary works, until a construction traffic management plan has been submitted to and, after consultation with North East Lincolnshire Council, Highways England and the highway authority, approved by the relevant planning authority.

(2) The plan submitted and approved must be in accordance with chapter 7 (traffic and transport) of the environmental statement and the framework construction traffic management plan.

(3) The plan submitted and approved must include—

(a)details of the routes to be used for the delivery of construction materials and any temporary signage to identify routes and promote their safe use, including details of the access points to the construction site to be used by light goods vehicles and heavy goods vehicles;

(b)details of the routing strategy and procedures for the notification and conveyance of abnormal invisible loads, including agreed routes, the numbers of abnormal loads to be delivered by road and measures to mitigate traffic impact; F4...

(c)any necessary measures for the temporary protection of carriageway surfaces, the protection of statutory undertakers' plant and equipment, and any temporary removal of street [F5furniture; and]

[F6(d) the construction programme.]

(4) Notices must be erected and maintained throughout the period of construction at every entrance to and exit from the construction site, indicating to drivers the approved routes for traffic entering and leaving the construction site.

(5) The plan must be implemented as approved unless otherwise agreed with the relevant planning authority.

Textual Amendments

F6Words in Sch. 2 para. 16(3)(d) inserted (17.5.2021) by The Immingham Open Cycle Gas Turbine (Correction) Order 2021 (S.I. 2021/581), art. 1, Sch.

Commencement Information

I16Sch. 2 para. 16 in force at 1.9.2020, see art. 1

Construction workers travel planE+W

17.—(1) No part of the authorised development may commence, save for the permitted preliminary works, until a construction workers travel plan has been submitted to and, after consultation with North East Lincolnshire Council, Highways England and the highway authority, approved by the relevant planning authority.

(2) The plan submitted and approved must be in accordance with chapter 7 (traffic and transport) of the environmental statement and the framework construction worker travel plan.

(3) The plan submitted and approved must include—

(a)measures to promote the use of sustainable transport to and from the authorised development by construction staff;

(b)provision as to the responsibility for, and timescales of, the implementation of those measures;

(c)details of parking for construction personnel within the construction sites; and

(d)a monitoring and review regime.

(4) The approved plan must be implemented prior to commencement of the authorised development, save for the permitted preliminary works, and must be maintained throughout the construction of the authorised development unless otherwise agreed with the relevant planning authority.

Commencement Information

I17Sch. 2 para. 17 in force at 1.9.2020, see art. 1

Construction hoursE+W

18.—(1) Construction work relating to the authorised development must not take place on bank holidays or otherwise outside the hours of—

(a)0700 to 1900 hours on Monday to Friday; and

(b)0800 to 1800 hours on a Saturday.

(2) Delivery or removal of materials, plant and machinery must not take place on bank holidays nor outside the hours of 0700 to 1900 hours on Monday to Saturday.

(3) The restrictions in sub-paragraphs (1) and (2) do not apply to construction work or the delivery or removal of materials, plant and machinery, where these—

(a)do not exceed a noise limit measured at the Order limits which has been agreed with the relevant planning authority;

(b)are carried out with the prior approval of the relevant planning authority; or

(c)are associated with an emergency.

(4) The restrictions in sub-paragraph (2) do not apply to the delivery of abnormal indivisible loads, which are—

(a)associated with an emergency; or

(b)carried out with the prior approval of the relevant planning authority.

(5) Sub-paragraph (1) does not preclude—

(a)a start-up period from 0630 to 0700 and a shut-down period from 1900 to 1930 Monday to Friday and a start-up period from 0730 to 0800 and a shut-down period from 1800 to 1830 on a Saturday; or

(b)maintenance at any time of plant and machinery engaged in the construction of the authorised development.

(6) In this requirement—

shut down period” means the period during which construction workers may return to the site office to return safety and other equipment, attend debrief sessions, change clothing and prepare to leave site; and

start-up period” means the period during which construction workers may arrive at site, sign in, don personal protective equipment, attend safety and other briefings and mobilise on site.

Commencement Information

I18Sch. 2 para. 18 in force at 1.9.2020, see art. 1

Control of noise - operationE+W

19.—(1) Prior to the date of final commissioning a scheme for the management and monitoring of noise during operation of the authorised development must be submitted to and approved by the relevant planning authority.

(2) The scheme submitted pursuant to sub-paragraph (1) must include the results of daytime and night time baseline noise monitoring that has been carried out by the undertaker for the purposes of this requirement as agreed with the relevant planning authority.

(3) Noise (in terms of the BS4142:2014 rating level) from the operation of the authorised development must be no greater than 3dB higher than the defined representative background sound level during each of the daytime and the night time, adjacent to the nearest residential properties at locations agreed with the relevant planning authority.

(4) The scheme must be implemented as approved unless otherwise agreed with the relevant planning authority.

(5) In this requirement—

(a)daytime” means the period from 0700 to 2300 and “night time” means the period from 2300 to 0700; and

(b)defined representative background sound level” means the sound level measured during the monitoring secured by sub-paragraph (2).

Commencement Information

I19Sch. 2 para. 19 in force at 1.9.2020, see art. 1

Piling and penetrative foundation designE+W

20.—(1) No part of the authorised development comprised within Work No. 1 may commence, save for the permitted preliminary works, until a written piling and penetrative foundation design method statement, informed by a risk assessment, for that part, has been submitted to and, after consultation with the Environment Agency, approved by the relevant planning authority.

(2) All piling and penetrative foundation works must be carried out in accordance with the approved method statement unless otherwise agreed with the relevant planning authority.

Commencement Information

I20Sch. 2 para. 20 in force at 1.9.2020, see art. 1

Waste management on site - construction wastesE+W

21.—(1) No part of the authorised development may commence, save for the permitted preliminary works, until a construction site waste management plan for that part has been submitted to and approved by the relevant planning authority.

(2) The plan submitted and approved must be in accordance with the principles set out in the framework construction environmental management plan.

(3) The plan must be implemented as approved unless otherwise agreed with the relevant planning authority.

Commencement Information

I21Sch. 2 para. 21 in force at 1.9.2020, see art. 1

Restoration of land used temporarily for constructionE+W

22.—(1) Prior to the date of final commissioning a scheme for the restoration of any land within the Order limits which has been used temporarily for construction must be submitted to and approved by the relevant planning authority.

(2) The land must be restored within three years of the date of final commissioning (or such other period as the relevant planning authority may approve), in accordance with the restoration scheme approved in accordance with sub-paragraph (1).

Commencement Information

I22Sch. 2 para. 22 in force at 1.9.2020, see art. 1

Employment, skills and training planE+W

23.—(1) No part of the authorised development may commence, save for the permitted preliminary works, until a plan detailing arrangements to promote employment, skills and training development opportunities for local residents during construction and employment opportunities during operation of the authorised development has been submitted to and, after consultation with North East Lincolnshire Council, approved by the relevant planning authority.

(2) The approved plan must be implemented and maintained during the construction and operation of the authorised development unless otherwise agreed with the relevant planning authority.

Commencement Information

I23Sch. 2 para. 23 in force at 1.9.2020, see art. 1

DecommissioningE+W

24.—(1) Within 12 months of the date that the undertaker decides to decommission the authorised development, the undertaker must submit to the relevant planning authority for their approval a decommissioning environmental management plan.

(2) No decommissioning works may be carried out until the relevant planning authority has approved the plan.

(3) The plan submitted and approved must include details of—

(a)the buildings to be demolished;

(b)the means of removal of the materials resulting from the decommissioning works;

(c)the phasing of the demolition and removal works;

(d)any restoration works to restore the land to a condition agreed with the relevant planning authority;

(e)the phasing of any restoration works; and

(f)a timetable for the implementation of the scheme.

(4) The plan must be implemented as approved unless otherwise agreed with the relevant planning authority.

Commencement Information

I24Sch. 2 para. 24 in force at 1.9.2020, see art. 1

Foul water drainageE+W

25.—(1) No part of the authorised development may commence, save for the permitted preliminary works, until full details of a scheme, for the connection, conveyance, treatment and disposal of mains foul water drainage on and off site has been submitted to, and after consultation with the Environment Agency and Anglian Water, approved by the relevant planning authority.

(2) If it is demonstrated as part of the information submitted pursuant to sub-paragraph (1) that it is not practicable or reasonable to connect to a mains system, an alternative strategy for the provision and implementation of wastewater treatment must be submitted to and, after consultation with the Environment Agency and Anglian Water, approved by the relevant planning authority. Any non-mains drainage proposal must include a management and maintenance plan to ensure that it will not cause pollution to the water environment.

(3) The schemes approved pursuant to sub-paragraph (1) and (where relevant) sub-paragraph (2) must be implemented and maintained throughout the operation of the authorised development unless otherwise agreed with the relevant planning authority.

Commencement Information

I25Sch. 2 para. 25 in force at 1.9.2020, see art. 1

Requirement for written approvalE+W

26.  Where under any of the above requirements the approval or agreement of the relevant planning authority or another person is required, that approval or agreement must be provided in writing.

Commencement Information

I26Sch. 2 para. 26 in force at 1.9.2020, see art. 1

Approved details and amendments to themE+W

27.—(1) All details submitted for approval of the relevant planning authority under these requirements must be in accordance with the parameters of the environmental statement and reflect the principles set out in the documents certified under article 39 (certification of plans etc.).

(2) With respect to any requirement which requires the authorised development to be carried out in accordance with the details approved by the relevant planning authority, the approved details are to be taken to include any amendments that may subsequently be approved by the relevant planning authority.

Commencement Information

I27Sch. 2 para. 27 in force at 1.9.2020, see art. 1

Amendments agreed by the relevant planning authorityE+W

28.—(1) Where the words “unless otherwise agreed with the relevant planning authority” appear in the above requirements, any such approval or agreement may only be given in relation to non-material amendments and where it has been demonstrated to the satisfaction of the relevant planning authority that the subject matter of the approval or agreement sought will not give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.

(2) In cases where the requirement or the relevant sub-paragraph requires consultation with specified persons, any approval or agreement must not be given without the relevant planning authority having first consulted with those persons.

Commencement Information

I28Sch. 2 para. 28 in force at 1.9.2020, see art. 1

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources