The Immingham Open Cycle Gas Turbine Order 2020

121.  Before commencing any part of the authorised development which would have an effect on the operation or maintenance of the pipeline and access to it, the undertaker must submit to Centrica plans and sections of the proposed works and such further particulars as Centrica may, within 28 days from the day on which plans and sections are submitted under this paragraph, reasonably require.E+W

Commencement Information

I1Sch. 9 para. 121 in force at 1.9.2020, see art. 1