Co-operation during constructionE+W

128.  The undertaker must not exercise the powers granted under this Order so as to hinder or prevent—

(a)the construction, operation, use or maintenance of the Able authorised development; or

(b)access to all parts of the Able authorised development,

otherwise than with the prior written consent of Able.

Commencement Information

I1Sch. 9 para. 128 in force at 1.9.2020, see art. 1

Back to top

Options/Help

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?