SCHEDULE 9PROTECTIVE PROVISIONS

PART 4FOR THE PROTECTION OF PHILLIPS 66 LIMITED

Authorisation of works details affecting pipelines or protected crossings37

No part of a relevant work is to be commenced until one of the following conditions has been satisfied—

a

the works details supplied in respect of that relevant work under paragraph 36 have been authorised by P66; or

b

the works details supplied in respect of that relevant work under paragraph 36 have been authorised by an expert under paragraph 39(3); or

c

authorisation is deemed to have been given in accordance with paragraph 39(1).