97.—(1) If P66 obtains a P66 planning permission for the development but does not give notice in accordance with paragraph 96 it must nevertheless notify the undertaker that a P66 planning permission has been obtained and provide a copy of it to the undertaker.
(2) If following receipt of the notice under sub-paragraph (1) the undertaker is of the reasonable opinion that the development would be likely to cause damage to the VPI apparatus or any interference with the exercise of the specified rights it may at its sole cost and expense divert the VPI apparatus or part thereof along the diversion route or carry out any such works as are described in paragraph 96(5)(a).
(3) Where the undertaker elects to carry out works under sub-paragraph (2) it is not required to implement any such works before the expiry of the period of six months from the date of the notice under sub-paragraph (1).
Back to top