Search Legislation

The A303 Sparkford to Ilchester Dualling Development Consent Order 2021

Changes over time for: SCHEDULE 5

 Help about opening options

Alternative versions:

Status:

Point in time view as at 19/02/2021.

Changes to legislation:

There are currently no known outstanding effects for the The A303 Sparkford to Ilchester Dualling Development Consent Order 2021, SCHEDULE 5. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Article 26

SCHEDULE 5E+WLAND IN WHICH ONLY NEW RIGHTS ETC. MAY BE PERMANENTLYACQUIRED

Commencement Information

I1Sch. 5 in force at 19.2.2021, see art. 1

(1) Plot reference number shown on land plans(2) Purpose for which rights over land may be acquired(3) Relevant part of the authorised development
1/2bTo plant and maintain hedgerows and undertake and maintain landscaping.Work Nos. 2 and 5
1/4aTo construct, operate and maintain a drainage outfall including access with or without vehicles.Work No. 6
2/2eTo construct and maintain a boundary fence, plant and maintain hedgerows and undertake and maintain landscaping, including planting.Work No. 11
3/1a

To undertake all works necessary to use the land for the ecological works including translocation of Great Crested Newts, reptiles and other species from the Order Land; and also including vegetation clearance, planting, landscaping, creation of a hibernacula, habitat improvement and the installation of fencing and access with or without vehicles to maintain the same.

To impose a restrictive covenant that the owner may not remove, damage, obstruct or interfere with any works undertaken for the purposes of using the land for the translocation of species from the Order Land for a period of five years from the date of opening of the Scheme.

Work No. 39
3/1b

To undertake all works necessary to use the land for the ecological works including translocation of Great Crested Newts, reptiles and other species from the Order Land; and also including vegetation clearance, planting, landscaping, creation of a hibernacula, habitat improvement and the installation of fencing and access with or without vehicles to maintain the same.

To impose a restrictive covenant that the owner may not remove, damage, obstruct or interfere with any works undertaken for the purposes of using the land for the translocation of species from the Order Land for a period of five years from the date of opening of the Scheme.

Work No. 40
3/2aTo construct, operate, access and maintain a way suitable for use by the public by bicycle and as a bridleway, including access with or without vehicles plant and machinery, and to designate that way as a Public Right of Way on its completion and allow public access over it.All works
4/1fTo construct, operate, access and maintain a way suitable for use by the public on foot, including access with or without vehicles plant and machinery, and to designate that way as a Public Right of Way on its completion and allow public access over it.Work No. 16
4/2aTo construct, operate, access and maintain a way suitable for use by the public on foot, including access with or without vehicles plant and machinery, and to designate that way as a Public Right of Way on its completion and allow public access over it.Work No. 16
4/4b

To designate the road to be formed on part of the plot as public highway open to vehicular traffic on its completion.

To construct, divert, use and maintain utility connections and equipment including electric cables, equipment and apparatus including access with or without vehicles.

Work Nos. 27, 38 and 38A
4/4gTo construct, operate, access and maintain a way suitable for use by the public by bicycle and as a bridleway, including access with or without vehicles plant and machinery, and to designate that way as a Public Right of Way on its completion and allow public access over it.All works
4/7aTo construct, operate, access and maintain a way suitable for use by the public by bicycle and as a bridleway, including access with or without vehicles plant and machinery, and to designate that way as a Public Right of Way on its completion and allow public access over it.All works
4/8bTo construct, operate and maintain a drainage outfall including access with or without vehicles.Work No. 29
5/1bTo construct, operate, access and maintain a way suitable for use by the public by bicycle and as a bridleway, including access with or without vehicles plant and machinery, and to designate that way as a Public Right of Way on its completion and allow public access over it.All works
5/3j

To designate the road to be formed on the plot as public highway open to vehicular traffic on its completion.

To construct, divert, use and maintain utility connections and equipment including electric cables, equipment and apparatus including access with or without vehicles.

Work Nos. 61 and 69
5/4cTo construct, divert, use and maintain utility connections and equipment including electric cables, equipment and apparatus including access with or without vehiclesWork No. 48
5/5cTo construct, divert, use and maintain utility connections and equipment including electric cables, equipment and apparatus including access with or without vehicles.Work No. 48
5/8bTo construct, operate, access and maintain a private means of access including creation of vehicular rights of access to the property served thereby.Work No. 52
5/9bTo construct, divert, use and maintain utility connections and equipment including telecommunication and electric cables, equipment and apparatus and water and sewerage pipes, equipment and apparatus including access with or without vehicles.Work Nos. 45, 46, 47, 48 and 74
6/1e

To undertake works to the local road and Camel Hill.

To construct, divert, use and maintain utility connections and equipment including telecommunication cables equipment and apparatus including access with or without vehicles.

Work Nos. 66 and 71
7/1cTo designate the road to be formed on the plot as public highway open to vehicular traffic on its completion.Work No. 62
7/5a

To designate the road to be formed on the plot as public highway open to vehicular traffic on its completion.

To construct, divert, use and maintain utility connections and equipment including electric cables and telecommunication cables equipment and apparatus including access with or without vehicles.

Work Nos. 63, 72 and 79
7/6aTo construct, operate, access and maintain a way suitable for use by the public as a footpath, including access with or without vehicles plant and machinery, and to designate that way as a Public Right of Way on its completion and allow public access over it.All works
7/7cTo designate the road to be formed on the plot as public highway open to vehicular traffic on its completion.Work No. 63
7/7dTo designate the road to be formed on the plot as public highway open to vehicular traffic on its completion.Work No. 63
7/8b

To construct, operate, access and maintain a way suitable for use by the public by bicycle and as a bridleway, including access with or without vehicles plant and machinery, and to designate that way as a Public Right of Way on its completion and allow public access over it.

To create a private right of access with or without vehicles, plant and machinery in favour of the owners of Blackwell Farm to take access over the plot for the purposes of agriculture.

To construct, divert, use and maintain utility connections and equipment including electric cables and telecommunication cables equipment and apparatus including access with or without vehicles.

Work Nos. 72 and 105
7/8cTo designate the road to be formed on the plot as public highway open to vehicular traffic on its completion.Work No. 64
8/2aTo construct, operate and maintain a drainage outfall including access with or without vehicles.Work No. 94
8/3aTo construct, improve, operate, access and maintain a way suitable for use by the public on foot and by bicycle including access with or without vehicles plant and machinery, and to designate that way as a Public Right of Way on its completion and allow public access over it.All works

Back to top

Options/Help

Print Options

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources