Search Legislation

The A303 Sparkford to Ilchester Dualling Development Consent Order 2021

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: SCHEDULE 7

 Help about opening options

Alternative versions:

Changes to legislation:

There are currently no known outstanding effects for the The A303 Sparkford to Ilchester Dualling Development Consent Order 2021, SCHEDULE 7. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Article 33

SCHEDULE 7E+WLAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

Commencement Information

I1Sch. 7 in force at 19.2.2021, see art. 1

(1) Plot Reference Number shown on land plans(2) Purpose for which temporary possession may be taken(3) Relevant part of the authorised development
1/3eWorking area and materials storageAll works
1/4cWorking area and materials storage, construction compoundsAll works
1/5aWorking area and materials storage, including for removal of existing carriageway and reinstatement of land as arable fieldWork No. 5
2/2bWorking area and materials storageAll works
2/2cDecommissioning of 75 metres of electrical cableWork No. 9
2/2dWorking area and materials storageAll works
2/4bWorking area and materials storageAll works
2/4cThe construction of B3151 link, works to the public highway, utility diversions under the public highwayWork Nos 16, 32 and 33
2/5bAccess to working area, materials storageAll works
2/5eWorking area and materials storage, construction compoundsAll works
3/2cWorking area and materials storageAll works
4/1cWorks associated with the closure of local road at Downhead, the construction of Downhead Turning Head, utility diversionsWork Nos. 27 and 38
4/1iThe construction of Downhead Lane and accesses, utility diversionsWork Nos. 17, 43 and 44
4/1jWorking area and materials storageAll works
4/4cWorking area and materials storageAll works
4/4dWorking area and materials storageAll works
4/5aThe decommissioning of overhead electrical cablesWork 38A
4/5bThe decommissioning of overhead electrical cablesWork No. 38A
4/8cTemporary highway diversionsAll works
4/8e

Temporary highway diversions

Construction and use of a temporary southern earthworks haul route

All works

Work 49

5/1aWorking area and materials storageAll works
5/3d

The construction of Steart Hill Link and Steart Hill North

Utility diversions

Work Nos. 41, 43, 44, 51 and 75
5/4aConstruction and use of a temporary southern earthworks haul routeWork No. 49
5/4bConstruction and use of a temporary southern earthworks haul routeWork No. 49
5/5bThe construction of Howell Hill Link (East)Work No. 42
5/7aConstruction and use of a temporary northern earthworks haul routeWork No. 80
5/7bLandscaping works and works to retain existing hedgerowAll works
5/7cWorking area for utility diversionsWork Nos. 45, 48 and 74
5/8cWorks to create alternative private means of accessWork No. 52
5/9cConstruction and use of a temporary southern earthworks haul routeWork No. 49
5/10aConstruction and use of a temporary northern earthworks haul routeWork No. 80
5/12aConstruction and use of a temporary northern earthworks haul routeWork No. 80
5/12bConstruction and use of a temporary northern earthworks haul routeWork No. 80
5/13bWorking area and materials storageAll works
6/1a

Works to local road junction at Camel Hill

Construction and use of a temporary northern earthworks haul route

Work Nos. 67 and 80
6/1bConstruction and use of a temporary northern earthworks haul routeWork No. 80
6/1cWorks to local road junction at Camel HillWork Nos. 66 and 67
6/1dWorks to local road junction at Camel HillWork No. 66
6/2aWorks to local road junction at Camel HillWork No. 67
6/3aDiversion of a public right of way in highway vergeAll works
7/1bWorking area and materials storageAll works
7/4cWorking area for utility diversionsWork No. 77
7/5b

Construction of new multi-purpose Track 10

Diversion of a public right of way and utilities

Work Nos. 72 and 105
7/5cWorking area to widen existing highway junctionWork No. 104
8/1a

Diversion of a public right of way

Utility diversions

All works

Work No. 84

8/1c

Diversion of a public right of way

Utility diversions

All works

Work No. 84

Back to top

Options/Help

Print Options

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources