Foul water drainageE+W+S

14.—(1) No part of the authorised development may commence, save for the permitted preliminary works, until details of the permanent foul water drainage systems, including a future maintenance plan, have been submitted to and, after consultation with Anglian Water and the Environment Agency, approved by the relevant planning authority.

(2) The details submitted and approved under sub-paragraph (1) must be in accordance with the principles set out in sections 2 and 5 of the outline drainage strategy.

(3) The scheme approved under sub-paragraph (1) must be implemented as approved prior to the development coming into operation and maintained as approved throughout the operation of the authorised development unless otherwise agreed by the relevant planning authority.

Commencement Information

I1Sch. 2 para. 14 in force at 2.12.2021, see art. 1