SCHEDULES

SCHEDULE 2E+W+SREQUIREMENTS

Approved details and amendments to themE+W+S

3.—(1) All relevant details submitted for the approval of the relevant planning authority pursuant to these requirements must be in accordance with the following dimensions—

(a)maximum main building height – 59 metres AOD (including 2 metre parapet wall on boiler house);

(b)maximum main building footprint – 210 metres x 110 metres;

(c)stack height – 102 metres AOD;

(d)maximum stack diameter – 3 metres per combustion stream; and

(e)bunker base maximum depth – -8 metres AOD.

(2) Where a requirement requires the authorised development to be constructed in accordance with details approved by the relevant planning authority, the approved details are taken to include any amendments subsequently approved by the relevant planning authority.