Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
2. The Building Regulations are amended in accordance with regulations 3 to 13.
3. In regulation 2(1) (interpretation)—
(a)in the definition of “energy efficiency requirements”, after “26B” insert, “, 26C”;
(b)after the definition of “softened wholesome water” insert—
“;
“system for on-site electricity generation” means a system that produces electricity and has a direct electrical connection to the building in question”.
4. In regulation 4 (requirements relating to building work), after paragraph (3) insert—
“(4) This paragraph applies in relation to a building where—
(a)building work is undertaken in respect of that building (“relevant work”); and
(b)Part L of Schedule 1 imposes a requirement in respect of the relevant work.
(5) Notwithstanding paragraph (3), upon completion of the relevant work, any building to which paragraph (4) applies must—
(a)comply with Part F of Schedule 1; or
(b)where the building did not comply with Part F of Schedule 1 before the relevant work was begun, be no more unsatisfactory in relation to it than before the work was begun.”.
5. In regulation 25 (minimum energy performance requirements for new buildings)—
(a)at the end of paragraph (a) omit “and”;
(b)after paragraph (b) insert—
“; and
(c)new buildings in the form of target primary energy rates”.
6. After regulation 26B (fabric performance values for new dwellings) insert—
26C. Where a building is erected it must not exceed the target primary energy rate for the building which has been approved pursuant to regulation 25(c), applying the methodology of calculation and expression of the energy performance of buildings approved pursuant to regulation 24.”.
7. After regulation 27B (fabric performance values calculations) insert—
27C.—(1) This regulation applies where a building is erected.
(2) Not later than the day before the work starts, the person carrying out the work must give the local authority a notice which specifies—
(a)the target primary energy rate for the building calculated and expressed in accordance with the methodology approved pursuant to regulation 24;
(b)the calculated target primary energy rate for the building as designed, calculated and expressed in accordance with the methodology approved pursuant to regulation 24; and
(c)a list of specifications to which the building is to be constructed.
(3) Not later than five days after the work has been completed, the person carrying out the work must give the local authority—
(a)a notice which specifies—
(i)the target primary energy rate for the building calculated and expressed in accordance with the methodology approved pursuant to regulation 24;
(ii)the calculated target primary energy rate for the building as constructed, calculated and expressed in accordance with the methodology approved pursuant to regulation 24; and
(iii)whether the building has been constructed in accordance with the list of specifications referred to in paragraph (2)(c), and if not a list of any changes to those specifications; or
(b)a certificate of the sort referred to in paragraph (4) accompanied by the information referred to in sub-paragraph (a).
(4) A local authority is authorised to accept, as evidence that the requirements of regulation 26C have been satisfied, a certificate to that effect by an energy assessor who is accredited to produce energy performance certificates for that category of building.
(5) In this regulation, “specifications” means specifications used for the calculation of the target primary energy rate.”.
8. After regulation 40 (information about use of fuel and power) insert—
40A.—(1) This regulation applies to building work in respect of a building in relation to which paragraph L2 of Schedule 1 applies.
(2) The person carrying out the work must, not later than five days after the work has been completed, provide to the owner sufficient information about the system for on-site electricity generation in respect of its operation and maintenance requirements so that the system may be operated and maintained in such a manner as to produce the maximum electricity that is reasonable in the circumstances and delivers this electricity to the optimal place for use.
40B.—(1) This regulation applies to building work in respect of a building where Part O of Schedule 1 applies.
(2) The person carrying out the work must, not later than five days after the work has been completed, give sufficient information to the owner about the provision made in accordance with Part O so that the systems in place further to Part O can be operated in such a manner as to protect against overheating.”.
9. In regulation 43(4) (pressure testing) for “the Independent Air Tightness Testing Scheme Limited” substitute “Elmhurst Energy Systems Limited”.
10. After regulation 44 (commissioning) insert—
44ZA.—(1) This regulation applies to building work in respect of a building in relation to which paragraph L2 of Schedule 1 imposes a requirement, but does not apply to the provision or extension of any system for on-site electricity generation where testing and adjustment is not possible.
(2) Where this regulation applies the person carrying out the work must, for the purpose of ensuring compliance with paragraph L2 of Schedule 1, give to the local authority a notice confirming that the system for on-site electricity generation has been commissioned.
(3) The notice must be given to the local authority—
(a)not later than the date on which the notice required by regulation 16(4) is required to be given; or
(b)where that regulation does not apply, not more than 30 days after completion of the work.”.
11. In Schedule 1 (requirements)—
(a)in entry L1, in paragraph (b)(i), after “are energy efficient” insert “to a reasonable standard”;
(b)after entry L1 insert—
“On-site generation of electricity | |
L2 | |
Where a system for on-site electricity generation is installed— (a) reasonable provision must be made to ensure that— (i) the system and its electrical output are appropriately sized for the site and available infrastructure; (ii) the system has effective controls; and (b) it must be commissioned by testing and adjusting as necessary to ensure that it produces the maximum electricity that is reasonable in the circumstances.”. |
(c)after entry N4 insert—
“PART O OVERHEATING | |
Overheating mitigation | |
O1 | |
(1) Reasonable provision must be made in respect of a dwelling, institution or any other building containing one or more rooms for residential purposes, other than a room in a hotel (“residences”) to— (a) limit unwanted solar gains in summer; (b) provide an adequate means to remove heat from the indoor environment. (2) In meeting the obligations in paragraph (1)— (a) account must be taken of the safety of any occupant, and their reasonable enjoyment of the residence; and (b) mechanical cooling may only be used where insufficient heat is capable of being removed from the indoor environment without it.”. |
12.—(1) Schedule 3 (self-certification schemes and exemptions from requirement to give building notice or deposit full plans) is amended as follows.
(2) In the table, in column 2 (person carrying out work)—
(a)in each of rows 7, 8 and 9 omit “, Building Engineering Services Competence Assessment Limited”;
(b)in each of rows 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 17, 18, 19 and 20 omit “or Stroma Certification Limited”;
(c)in row 2 after “NAPIT Registration Limited”, for “,” substitute “or”;
(d)in row 3 after “NAPIT Registration Limited”, for “,” substitute “or”;
(e)in row 4 after “NAPIT Registration Limited”, for “,” substitute “or”;
(f)in row 5 after “Certsure LLP”, for “,” substitute “or”;
(g)in row 6 after “Certsure LLP”, for “,” substitute “or”;
(h)in row 7 after “Certsure LLP”, for “,” substitute “or”;
(i)in row 8 after “NAPIT Registration Limited, for “,” substitute “or”;
(j)in row 9 after “Certsure LLP”, for “,” substitute “or”;
(k)in row 10 after “Fenestration Self-Assessment Scheme”, for “,” substitute “or”;
(l)in row 11 after “Fenestration Self-Assessment Scheme”, for “,” substitute “or”;
(m)in row 12 after “HETAS Limited”, for “,” substitute “or”;
(n)in row 13 after “HETAS Limited”, for “,” substitute “or”;
(o)in row 14 after “HETAS Limited”, for “,” substitute “or”;
(p)in row 15 after “NAPIT Registration Limited”, for “,” substitute “or”;
(q)in row 17—
(i)for “Cavity Insulation Guarantee Agency” substitute “Insulation Assurance Authority Limited”;
(ii)after “Certsure LLP”, for “,” substitute “or”;
(r)in row 18 after “Certsure LLP”, for “,” substitute “or”;
(s)in row 19 after “Certsure LLP”, for “,” substitute “or”;
(t)in row 20 after “Certsure LLP”, for “,” substitute “or”.
13. In Schedule 3A (third party certification schemes and exemptions from requirement to give building notice or deposit full plans), in column 2 (person inspecting work) of the table omit “, or Stroma Certification Limited”.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: