SCHEDULES

SCHEDULE 2REQUIREMENTS

PART 1REQUIREMENTS

Combined heat and power

13.—(1) Within 12 months of ceasing to supply heat and/or power to the Kemsley Paper Mill, the undertaker must submit to the relevant planning authority for its approval a strategy (“the CHP strategy”).

(2) The CHP strategy submitted and approved must—

(a)consider the opportunities that reasonably exist at the time of submission for the export of heat and/or power from the K3 Generating Station to other users; and

(b)include a list of actions (if any) that the undertaker is reasonably to take (without material additional cost to the undertaker) to increase the potential for the export of heat from the K3 Generating Station to other users.

(3) The undertaker must take such actions as are included, within the timescales specified, in the approved CHP strategy.