2021 No. 535

Infrastructure Planning

The Rampion Offshore Wind Farm (Amendment) Order 2021

Made

Coming into force

An application has been made, under paragraph 2 of Schedule 6 to the Planning Act 20081, to the Secretary of State in accordance with Part 1 of the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 20112 (the “2011 Regulations”) for a non-material change to the Rampion Offshore Wind Farm Order 2014 (the “2014 Order”)3.

The Secretary of State, having considered the application, the responses to the publicity and the consultation required by Regulations 6 and 7 of the 2011 Regulations, has decided to make this Order amending the 2014 Order.

Accordingly, the Secretary of State, in exercise of the powers in paragraph 2 of Schedule 6 to the Planning Act 2008, makes the following Order—