xmlns:atom="http://www.w3.org/2005/Atom"

Amendments to Part 1 (Authorised Development) of Schedule 1 (Authorised Project)

3.  In Part 1 (Authorised development) of Schedule 1 (Authorised project), in paragraph (a) of the description of Work No. 1—

(a)for “with an electrical export capacity of up to 1,800 MW at the point of connection to the offshore electrical platform(s) referred to at Work No. 2” substitute “with a gross electrical output of over 100 MW”; and

(b)for “up to 158 wind turbine generators” substitute “up to 145 wind turbine generators”.