The A47/A11 Thickthorn Junction Development Consent Order 2022

Article 39

SCHEDULE 8E+W+SREMOVAL OF HEDGEROWS

PART 1E+W+SREMOVAL OF HEDGEROWS

Commencement Information

I1Sch. 8 Pt. 1 in force at 4.11.2022, see art. 1

(1)

Location of hedgerow

(2)

Work to be carried out

(3)

Relevant part of the authorised development

H5 to H5 shown on sheet 3 of the Hedgerow PlansPartial removalWork No. 2
H8 to H8 shown on sheet 5 of the Hedgerow PlansPartial removalWork No. 1
H9 to H9 shown on sheet 5 of the Hedgerow PlansFull removalWork Nos. 1 and 2

PART 2E+W+SREMOVAL OF IMPORTANT HEDGEROWS

Commencement Information

I2Sch. 8 Pt. 2 in force at 4.11.2022, see art. 1

(1)

Location of hedgerow

(2)

Work to be carried out

(3)

Relevant part of the authorised development

H6 to H6 shown on sheet 3 of the Hedgerow PlansPartial removal and translocationWork No. 12