SCHEDULES
SCHEDULE 9PROTECTIVE PROVISIONS
PART 3FOR THE PROTECTION OF NATIONAL GRID AS ELECTRICITY UNDERTAKER
Notices
32.
Notwithstanding article 50 (service of notices), any plans submitted to National Grid by the undertaker pursuant to paragraph 25 (retained apparatus: protection of electricity undertaker) must be sent to https://lsbud.co.uk/ and National Grid Plant Protection at plantprotection@nationalgrid.com or such other address as National Grid may from time to time appoint instead for that purpose and notify to the undertaker in writing.