PART 2E+W+SPass-through requirement

Pass-through requirementE+W+S

3.—(1) A relevant intermediary must not—

(a)in its capacity as an EPG consumer reject an EPG tariff reduction offered to it pursuant to section 8.4(b)(i) of F1... the EPG scheme documents, or

(b)reject, or fail to take all reasonable steps in accordance with paragraph (10) to secure, a pass-through amount to which it is entitled pursuant to the operation of these Regulations.

(2) A relevant intermediary must ensure that as soon as reasonably practicable after a scheme benefit has been provided to it in respect of a period, it provides to each of its end users in respect of that period a just and reasonable pass-through amount in respect of the scheme benefit provided to that relevant intermediary.

(3) If and to the extent that the relevant intermediary does not pass through the whole of the scheme benefit provided to it in a period to its end users, it is for the relevant intermediary to demonstrate to end users that the pass-through it has effected in respect of the period concerned is just and reasonable, and in so doing it is entitled to take into account the extent to which its charges to end users reflect the increased cost of energy as a result of the energy crisis.

(4) The pass-through amount must be calculated in accordance with the rules set out in regulation 4.

(5) Unless the circumstances in paragraph (7) apply, a scheme benefit is provided to a relevant intermediary—

(a)if such scheme benefit is an EBSS scheme benefit, when the EBSS support payment is provided to it by an EBSS domestic electricity supplier pursuant to the provisions of paragraph 9 of the EBSS Direction,

(b)if such scheme benefit is an EPG scheme benefit, at the start of an EPG tariff period in which it has been notified of an EPG tariff reduction in its capacity as an EPG consumer pursuant to section 8.2 of F2... the EPG scheme documents, or

(c)if the relevant intermediary is also an end user, when a pass-through amount is provided to it by virtue of these Regulations.

(6) A scheme benefit is deemed to have been provided to a relevant intermediary when such relevant intermediary is notified that it has been identified as an end user for the purpose of these Regulations but the pass-through amount set out in such notification is zero.

(7) A scheme benefit is not treated as having been provided to a relevant intermediary for the purposes of these Regulations to the extent that the relevant intermediary has notified the person that provided the scheme benefit that it has been provided in error and the relevant intermediary is taking reasonable steps to return such scheme benefit to that person in accordance with the requirements of the EBSS or EPG (as appropriate).

(8) An end user can also be a relevant intermediary in respect of a scheme benefit provided to that end user and vice versa.

(9) Where a person is an end user, and that person is also a relevant intermediary in respect of some or all of the same energy, that person must comply with these Regulations.

(10) To give full effect to the pass-through requirement a relevant intermediary must take all such reasonable steps as may be necessary to secure that it is provided with the scheme benefit to which it is entitled so that it may effect a pass-through to its end users.

Calculation of pass-through amountE+W+S

4.—(1) Subject to regulation 3(3), the requirement for a relevant intermediary to provide to end users a pass-through amount that is just and reasonable is treated as having been met in any case where—

(a)the relevant intermediary makes energy available through equipment where—

(i)tariffs per unit of energy used are automatically charged by the equipment; and

(ii)the energy is paid for by end users at the time that the energy is made available; and

(b)the relevant intermediary effects a pass-through by, as soon as reasonably practicable after the scheme benefit is provided to the relevant intermediary in accordance with regulation 3(5), adjusting the tariffs charged by the equipment to reflect—

(i)if the scheme benefit concerned is an EPG scheme benefit, the EPG tariff reduction, or

(ii)in all other cases, the relevant intermediary’s reasonable assessment using best available information of the adjustment required to allocate the scheme benefit between the relevant intermediary’s end users in accordance with paragraph (2) or (3) below (as appropriate),

(2) Subject to regulation 3(3), where the relevant intermediary was charging end users at the point at which the scheme benefit was provided to it either—

(a)according to the proportion which each end user’s usage represents of the aggregate quantity of energy supplied or made available to the relevant intermediary which led to provision of the scheme benefit, or

(b)according to the proportion each end user pays of the total amount paid by the relevant intermediary in relation to the aggregate energy supplied or made available to the relevant intermediary which led to provision of the scheme benefit,

a pass-through amount is just and reasonable for the purposes of regulation 3(2), if the relevant intermediary applies the same approach, as the case may be, to calculate the pass-through amount for each end user on this basis.

(3) If neither paragraph (1) nor paragraph (2) applies, in considering what is just and reasonable the relevant intermediary must apply the best available information to allocate the benefit amongst end users and in so doing may take into account the basis on which the relevant intermediary was allocating charges amongst end users at the point at which the scheme benefit was provided to it.

(4) When calculating the pass-through amount in accordance with this regulation, a relevant intermediary must take into account circumstances in which a person is an end user for part of a period, such that the pass-through to that end user relates only to that part of the relevant period in which they were an end user.

(5) A relevant intermediary is not required to pass-through to end users amounts in excess of the scheme benefit provided to it (as adjusted to take account of its own end user usage, where relevant).

(6) When calculating pass-through amounts, a relevant intermediary which is also an end user in respect of a scheme benefit provided to it must not retain more of the scheme benefit for itself than is proportionate to its own usage (or, if it is not practicable to assess the volume of its usage, the proportion of overall energy charges borne by the relevant intermediary and its end users that the relevant intermediary itself bears).

(7) A relevant intermediary is entitled to include energy used to provide common services to end users as part of its own usage for the purposes of the calculation in paragraphs (2) or (3) to the extent that the cost of such energy is or will not be borne by its end users as part of the arrangements in place when the scheme benefit was provided to the relevant intermediary in accordance with regulation 3(5).

Commencement Information

I2Reg. 4 in force at 1.11.2022, see reg. 1(1)

Provision of information to end usersE+W+S

5.—(1) Within the period of 30 days beginning with the later of the day on which these Regulations came into force or the day on which the scheme benefit was provided to it in accordance with regulation 3(5) or was deemed to have been provided to it in accordance with regulation 3(6), the relevant intermediary must take reasonable steps to notify its end users in writing (where possible using the means of communication it customarily uses to communicate with its end users)—

(a)that the relevant intermediary has either—

(i)had a scheme benefit provided to it and has identified the end user as a person entitled to a just and reasonable proportion of such benefit by virtue of the application of these Regulations, or

(ii)been notified that it has been identified as an end user for the purpose of these Regulations but the pass-through amount set out in such notification is zero (and in such circumstances the relevant intermediary must also provide to its end users the details in sub-paragraphs (b) and (c) provided to it in the notice from its relevant intermediary and the information set out in sub-paragraphs (f) and (g)),

(b)the amount of scheme benefit provided to the relevant intermediary and whether the scheme benefit is an EBSS scheme benefit or an EPG scheme benefit,

(c)the amount or proportion of scheme benefit provided to the relevant intermediary (if any) which it intends to pass-through to the end user concerned together with supporting details demonstrating why the relevant intermediary considers such pass-through amount to be just and reasonable,

(d)to the extent applicable, when and how the relevant intermediary will provide the pass-through amount to the end user,

(e)to the extent applicable, of any steps it is taking to correct an error in the way in which the relevant intermediary has previously passed-through a scheme benefit to an end user,

(f)how the end user may appeal to the relevant intermediary about the matters set out in the notice, and

(g)that if the pass-through amount to which it is entitled by virtue of these Regulations is not provided to the end user, it is entitled to recover it from the relevant intermediary as a civil debt pursuant to regulation 7(1).

(2) Where the relevant intermediary makes energy available through equipment which automatically charges a tariff per unit of energy used, paid by end users at the time the energy is made available—

(a)paragraph (1) does not apply, and

(b)the relevant intermediary must, as soon as reasonably practicable after the scheme benefit was provided to it, notify its end users by notice on or near such equipment in a place in which it will be seen by end users of—

(i)the tariff adjustment which the relevant intermediary has applied pursuant to these Regulations to effect the pass-through to end users of the scheme benefit which has been provided to it, and

(ii)the contact details of the relevant intermediary which can be used should the end user require further information about its entitlements under these Regulations, including the ability to appeal to the relevant intermediary in respect of the basis on which the tariffs have been adjusted to reflect the scheme benefit provided to the relevant intermediary.

Commencement Information

I3Reg. 5 in force at 1.11.2022, see reg. 1(1)

Effecting the pass-throughE+W+S

6.—(1) Notwithstanding any provision in the contract between the relevant intermediary and the end user at the time the scheme benefit was provided to the relevant intermediary, the relevant intermediary must effect the pass-through so that the pass-through amount is provided to the end user as soon as reasonably practicable.

(2) Where the relevant intermediary makes energy available through equipment which automatically charges a tariff per unit of energy used, paid by end users at the time that the energy is made available, the relevant intermediary must as soon as reasonably practicable make such adjustments to its tariff as is necessary to effect the pass-through required under regulation 3(2).

(3) Without prejudice to paragraph (1), a pass-through can be effected, in pounds sterling or pounds sterling per [F3kWh] by—

(a)application of a credit in the next invoice, statement of account or other similar document provided by the relevant intermediary to the end user,

(b)a payment in cash or by any other means, including a bank transfer,

(c)tariff adjustment on tariff equipment,

(d)adjusting the amount of money taken pursuant to a direct debit or the amount of a standing order,

(e)set off against an amount or part of an amount which was owed by the end user to the relevant intermediary at the time at which the scheme benefit was provided to the relevant intermediary in accordance with regulation 3(5),

or a combination of the methods set out in this paragraph, as appropriate.

(4) A relevant intermediary has discharged its duty under regulations 3(2), 5(1) or 5(2), and paragraph (1) in respect of an end user if and to the extent it has taken reasonable steps to notify and effect a pass-through of a just and reasonable pass-through amount to that end user but is unable to do so.

(5) An end user has no right to a pass-through amount if the relevant intermediary has discharged its duty under regulations 3(2), 5(1) or 5(2), and paragraph (1) pursuant to paragraph (4) and a period of six months has elapsed after the scheme benefit concerned was provided to the relevant intermediary.

(6) If the contract between the relevant intermediary and the end user expires or is terminated before the pass-through required by these Regulations is effected (such that the full value of the pass-through amount has not been provided to the end user), the relevant intermediary must effect a pass through to the end user to reflect the end user’s entitlement (or remaining entitlement) under these Regulations as soon as reasonably practicable following such expiry or termination.