- Latest available (Revised)
- Original (As made)
There are currently no known outstanding effects for the The Norfolk Vanguard Offshore Wind Farm Order 2022, Paragraph 16.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
16.—(1) The total number of converter buildings for the onshore project substation must not exceed two.
(2) Construction works for the converter buildings referred to in paragraph (1) above must not commence until details of the layout, scale and external appearance of the same have been submitted to and approved by the relevant planning authority.
(3) The onshore project substation must be carried out in accordance with the approved details.
(4) Any details provided by the undertaker pursuant to paragraph (2) must:
(a)accord with the design and access statement;
(b)be supported by a statement illustrating how the details submitted accord with the principles of the OPS Masterplan and have been informed by a strategic approach to mitigate cumulative impacts arising from the onshore project substation and the Norfolk Boreas onshore project substation;
(c)have been subject to an early independent design review which must consider whether the requirements of sub-paragraphs (a) and (b) have been satisfied and make recommendations for design improvements if not; and
(d)be within the Order limits.
(5) Buildings (including the converter buildings) comprised in Work No. 8A must not exceed a height of 19 metres above existing ground level and external electrical equipment comprised in Work No. 8A must not exceed a height of 25 metres above existing ground level.
(6) The total footprint of each converter building must not exceed 110 metres by 70 metres.
(7) The fenced compound area (excluding its accesses) for the onshore project substation comprised in Work No. 8A must not exceed 250 metres by 300 metres.
(8) For the purposes of subparagraph (5) of this requirement ‘existing ground level’ means 71 metres above ordnance datum.
(9) The external electrical equipment comprised in Work No. 10A must not exceed a height of 15 metres above existing ground level.
(10) For the purposes of subparagraph (9) of this requirement ‘existing ground level’ means 69 metres above ordnance datum.
(11) The fenced compound area (excluding its accesses) for the extension to the Necton National Grid substation comprised in Work No. 10A must not exceed 200 metres by 150 metres.
(12) Construction works for the permanent replacement overhead pylons comprised in Work No. 11 must not commence until details of the same have been submitted to and approved by the relevant planning authority.
(13) The permanent replacement overhead line pylon works comprised in Work No. 11 must be carried out in accordance with the approved details.
(14) The permanent replacement overhead line pylons comprised in Work No. 11 must not exceed a height of 55 metres above existing ground level.
(15) The total footprint of each permanent replacement overhead line pylon comprised in Work No. 11 must not exceed 25 metres by 25 metres.
(16) For the purposes of subparagraph (14) of this requirement ‘existing ground level’ means between 66 and 69 metres above ordnance datum in respect of the eastern pylon identified on work plan 41 of 42 with the letter ‘E’ and between 68 and 70 metres above ordnance datum in respect of the eastern pylon identified on work plan 41 of 42 with the letter ‘W’.
(17) Trenchless installation techniques must be used for the purposes of passing under—
(a)the River Wensum (Work No. 7);
(b)King’s Beck (Work No. 5);
(c)Wendling Beck (Work No. 7);
(d)River Bure (Work No. 6);
(e)North Walsham and Dilham Canal (Work No. 5);
(f)the Witton Hall Plantation along Old Hall Road (Work No. 5);
(g)the Wendling Carr County Wildlife Site (Work No. 7);
(h)Little Wood County Wildlife Site (Work No. 7);
(i)land south of the Dillington Carr County Wildlife Site (Work No. 7);
(j)Kerdiston proposed County Wildlife Site (Work No. 6);
(k)Marriott’s Way County Wildlife Site/ Public Right of Way (Work No. 6);
(l)Paston Way and Knapton Cutting County Wildlife Site (Work No. 5);
(m)Norfolk Coast Path (Work No. 4C);
(n)Norwich to Cromer railway line at north Walsham (Work No. 5);
(o)Wymondham to North Elmham Railway line at Dereham (Work No. 7);
(p)A47 Road (Work No. 7);
(q)A140 Road (Work No. 6);
(r)A149 Road (Work No. 5);
(s)A1067 Road (Work No. 7); and
(t)F1... B1149 (Work No. 6).
(18) The number of underground cable ducts to be installed at the landfall [F2must not exceed four].
Textual Amendments
F1Words in Sch. 1 Pt. 3 omitted (7.9.2022) by virtue of The Norfolk Vanguard Offshore Wind Farm (Corrections) Order 2022 (S.I. 2022/944), art. 1(2), Sch.
F2Words in Sch. 1 Pt. 3 para. 16(18) substituted (14.12.2023) by The Norfolk Vanguard Offshore Wind Farm (Amendment) Order 2023 (S.I. 2023/1390), arts. 1, 3
Commencement Information
I1Sch. 1 para. 16 in force at 5.3.2022, see art. 1
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: