PART 3STREETS
Agreements with street authoritiesI113
1
A street authority and the undertaker may enter into agreements with respect to—
a
the construction of any new street including any structure carrying the street over or under any part of the authorised development;
b
the strengthening, improvement, repair or reconstruction of any street under the powers conferred by this Order;
c
the maintenance of the structure of any bridge or tunnel carrying a street;
d
any stopping up, prohibition, restriction, alteration or diversion of a street authorised by this Order;
e
the undertaking in the street of any of the works referred to in article 11(1) (construction and maintenance of new or altered means of access); or
f
the adoption by a street authority which is the highway authority of works—
i
undertaken on a street which is existing publicly maintainable highway; or
ii
which the undertaker and highway authority agree are to be adopted as publicly maintainable highway.
2
If such an agreement provides that the street authority must undertake works on behalf of the undertaker the agreement may, without prejudice to the generality of paragraph (1)—
a
make provision for the street authority to carry out any function under this Order which relates to the street in question;
b
specify a reasonable time for the completion of the works; and
c
contain such terms as to payment and otherwise as the parties consider appropriate.