http://www.legislation.gov.uk/uksi/2022/1396/introduction/2023-04-20The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022enINFRASTRUCTURE PLANNINGStatute Law Database2024-05-20Expert Participation2023-04-20This Order authorises the undertaker (referred to in this Order as the undertaker) to construct, operate and maintain a power generating station and carbon capture and compression plant. The Order permits the undertaker to acquire, compulsorily or by agreement, land and rights in land and to use land for this purpose.Statutory Instruments2022 No. 1396Infrastructure PlanningThe Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022Made7th December 2022Coming into force29th December 2022

An application has been made to the Secretary of State under section 37 of the Planning Act 2008

2008 c. 29. Parts 1 to 7 were amended by Chapter 6 of Part 6 of the Localism Act 2011 (c. 20). Part 7 was amended by S.I. 2017/16.

(“the 2008 Act”) in accordance with the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009

S.I. 2009/2264, as amended by S.I. 2012/635 and S.I. 2013/522. There are other amendments to the Regulations which are not relevant to this Order.

for an order granting development consent.

The application has been examined by the Examining Authority appointed by the Secretary of State pursuant to Chapter 3 of Part 6 of the 2008 Act. The examination was carried out in accordance with Chapter 4 of Part 6 of the 2008 Act and the Infrastructure Planning (Examination Procedure) Rules 2010

S.I. 2010/103 amended by S.I. 2012/635.

. The Examining Authority has submitted a report and recommendation to the Secretary of State under section 83 of the 2008 Act.

The Secretary of State has considered the report and recommendations of the Examining Authority, has considered the environmental information in accordance with regulation 4 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2017

S.I. 2017/572 amended by S.I. 2018/695, S.I. 2018/942.

and has had regard to the documents and matters referred to in section 104(2)

Section 104 was amended by section 58(5) of the Marine and Coastal Access Act 2009 (c. 23) and by section 128(2) and Schedule 13, paragraphs 1 and 49(1) to (6) of the Localism Act 2011 (c. 20).

of the 2008 Act.

The Secretary of State, having decided the application, has determined to make an order giving effect to the proposals comprised in the application on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.

Accordingly, the Secretary of State, in exercise of the powers conferred by sections 114, 115, 120 and 149A of the 2008 Act, makes the following Order—

This XML file does not appear to have any style information associated with it. The document tree is shown below.
<akomaNtoso xmlns:uk="https://www.legislation.gov.uk/namespaces/UK-AKN" xmlns:ukl="http://www.legislation.gov.uk/namespaces/legislation" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xmlns="http://docs.oasis-open.org/legaldocml/ns/akn/3.0" xsi:schemaLocation="http://docs.oasis-open.org/legaldocml/ns/akn/3.0 http://docs.oasis-open.org/legaldocml/akn-core/v1.0/cos01/part2-specs/schemas/akomantoso30.xsd">
<act name="uksi">
<meta>
<identification source="#">
<FRBRWork>
<FRBRthis value="http://www.legislation.gov.uk/id/uksi/2022/1396"/>
<FRBRuri value="http://www.legislation.gov.uk/id/uksi/2022/1396"/>
<FRBRdate date="2022-12-07" name="made"/>
<FRBRauthor href="http://www.legislation.gov.uk/id/government/uk"/>
<FRBRcountry value="GB-UKM"/>
<FRBRsubtype value="order"/>
<FRBRnumber value="1396"/>
<FRBRname value="S.I. 2022/1396"/>
<FRBRprescriptive value="true"/>
</FRBRWork>
<FRBRExpression>
<FRBRthis value="http://www.legislation.gov.uk/uksi/2022/1396/2023-04-20"/>
<FRBRuri value="http://www.legislation.gov.uk/uksi/2022/1396/2023-04-20"/>
<FRBRdate date="2023-04-20" name="validFrom"/>
<FRBRauthor href="#"/>
<FRBRlanguage language="eng"/>
</FRBRExpression>
<FRBRManifestation>
<FRBRthis value="http://www.legislation.gov.uk/uksi/2022/1396/2023-04-20/data.akn"/>
<FRBRuri value="http://www.legislation.gov.uk/uksi/2022/1396/2023-04-20/data.akn"/>
<FRBRdate date="2024-11-25Z" name="transform"/>
<FRBRauthor href="http://www.legislation.gov.uk"/>
<FRBRformat value="application/akn+xml"/>
</FRBRManifestation>
</identification>
<lifecycle source="#">
<eventRef refersTo="#made" date="2022-12-07" eId="date-made" source="#"/>
<eventRef refersTo="#coming-into-force" date="2022-12-29" eId="date-cif-1" source="#"/>
<eventRef date="2022-12-29" eId="date-2022-12-29" source="#"/>
<eventRef date="2023-04-20" eId="date-2023-04-20" source="#"/>
</lifecycle>
<analysis source="#">
<restrictions source="#">
<restriction refersTo="#extent-e+w+s" type="jurisdiction"/>
<restriction href="#preface" refersTo="#extent-e+w+s" type="jurisdiction"/>
<restriction refersTo="#period-from-2023-04-20" type="jurisdiction"/>
<restriction href="#preface" refersTo="#period-from-2022-12-29" type="jurisdiction"/>
</restrictions>
<otherAnalysis source=""/>
</analysis>
<temporalData source="#">
<temporalGroup eId="period-from-2022-12-29">
<timeInterval start="#date-2022-12-29" refersTo="#"/>
</temporalGroup>
<temporalGroup eId="period-from-2023-04-20">
<timeInterval start="#date-2023-04-20" refersTo="#"/>
</temporalGroup>
</temporalData>
<references source="#">
<TLCEvent eId="made" href="" showAs="Made"/>
<TLCEvent eId="cif" href="" showAs="ComingIntoForce"/>
<TLCLocation eId="extent-e+w+s" href="" showAs="E+W+S"/>
</references>
<proprietary xmlns:ukm="http://www.legislation.gov.uk/namespaces/metadata" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:dct="http://purl.org/dc/terms/" source="#">
<dc:identifier>http://www.legislation.gov.uk/uksi/2022/1396/introduction/2023-04-20</dc:identifier>
<dc:title>The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022</dc:title>
<dc:language>en</dc:language>
<dc:subject scheme="SIheading">INFRASTRUCTURE PLANNING</dc:subject>
<dc:publisher>Statute Law Database</dc:publisher>
<dc:modified>2024-05-20</dc:modified>
<dc:contributor>Expert Participation</dc:contributor>
<dct:valid>2023-04-20</dct:valid>
<dc:description>This Order authorises the undertaker (referred to in this Order as the undertaker) to construct, operate and maintain a power generating station and carbon capture and compression plant. The Order permits the undertaker to acquire, compulsorily or by agreement, land and rights in land and to use land for this purpose.</dc:description>
<ukm:SecondaryMetadata>
<ukm:DocumentClassification>
<ukm:DocumentCategory Value="secondary"/>
<ukm:DocumentMainType Value="UnitedKingdomStatutoryInstrument"/>
<ukm:DocumentStatus Value="revised"/>
<ukm:DocumentMinorType Value="order"/>
</ukm:DocumentClassification>
<ukm:Year Value="2022"/>
<ukm:Number Value="1396"/>
<ukm:Made Date="2022-12-07"/>
<ukm:ComingIntoForce>
<ukm:DateTime Date="2022-12-29"/>
</ukm:ComingIntoForce>
<ukm:ISBN Value="9780348243307"/>
</ukm:SecondaryMetadata>
<ukm:Alternatives>
<ukm:Alternative URI="http://www.legislation.gov.uk/uksi/2022/1396/pdfs/uksi_20221396_en.pdf" Date="2022-12-28" Size="684505"/>
</ukm:Alternatives>
<ukm:Statistics>
<ukm:TotalParagraphs Value="262"/>
<ukm:BodyParagraphs Value="45"/>
<ukm:ScheduleParagraphs Value="217"/>
<ukm:AttachmentParagraphs Value="0"/>
<ukm:TotalImages Value="0"/>
</ukm:Statistics>
</proprietary>
</meta>
<preface eId="preface" uk:target="true">
<block name="banner">Statutory Instruments</block>
<block name="number">
<docNumber>2022 No. 1396</docNumber>
</block>
<container name="subjects">
<container name="subject">
<block name="subject">
<concept refersTo="#">Infrastructure Planning</concept>
</block>
</container>
</container>
<block name="title">
<docTitle>The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022</docTitle>
</block>
<container name="dates">
<block name="madeDate" refersTo="#date-made">
<span>Made</span>
<docDate date="2022-12-07">7th December 2022</docDate>
</block>
<block name="commenceDate" refersTo="#date-cif-1">
<span>Coming into force</span>
<docDate date="2022-12-29">29th December 2022</docDate>
</block>
</container>
</preface>
<preamble>
<p>
An application has been made to the Secretary of State under section 37 of the Planning Act 2008
<authorialNote class="footnote" eId="f00001" marker="1">
<p>
<ref eId="c00001" href="http://www.legislation.gov.uk/id/ukpga/2008/29">2008 c. 29</ref>
. Parts 1 to 7 were amended by Chapter 6 of Part 6 of the Localism Act
<ref eId="c00002" href="http://www.legislation.gov.uk/id/ukpga/2011/20">2011 (c. 20)</ref>
. Part 7 was amended by
<ref eId="c00003" href="http://www.legislation.gov.uk/id/uksi/2017/16">S.I. 2017/16</ref>
.
</p>
</authorialNote>
(“
<term refersTo="#term-the-2008-act" eId="term-the-2008-act">the 2008 Act</term>
”) in accordance with the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009
<authorialNote class="footnote" eId="f00002" marker="2">
<p>
<ref eId="c00004" href="http://www.legislation.gov.uk/id/uksi/2009/2264">S.I. 2009/2264</ref>
, as amended by
<ref eId="c00005" href="http://www.legislation.gov.uk/id/uksi/2012/635">S.I. 2012/635</ref>
and
<ref eId="c00006" href="http://www.legislation.gov.uk/id/uksi/2013/522">S.I. 2013/522</ref>
. There are other amendments to the Regulations which are not relevant to this Order.
</p>
</authorialNote>
for an order granting development consent.
</p>
<p>
The application has been examined by the Examining Authority appointed by the Secretary of State pursuant to Chapter 3 of Part 6 of the 2008 Act. The examination was carried out in accordance with Chapter 4 of Part 6 of the 2008 Act and the Infrastructure Planning (Examination Procedure) Rules 2010
<authorialNote class="footnote" eId="f00003" marker="3">
<p>
<ref eId="c00007" href="http://www.legislation.gov.uk/id/uksi/2010/103">S.I. 2010/103</ref>
amended by
<ref eId="c00008" href="http://www.legislation.gov.uk/id/uksi/2012/635">S.I. 2012/635</ref>
.
</p>
</authorialNote>
. The Examining Authority has submitted a report and recommendation to the Secretary of State under section 83 of the 2008 Act.
</p>
<p>
The Secretary of State has considered the report and recommendations of the Examining Authority, has considered the environmental information in accordance with regulation 4 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2017
<authorialNote class="footnote" eId="f00004" marker="4">
<p>
<ref eId="c00009" href="http://www.legislation.gov.uk/id/uksi/2017/572">S.I. 2017/572</ref>
amended by
<ref eId="c00010" href="http://www.legislation.gov.uk/id/uksi/2018/695">S.I. 2018/695</ref>
,
<ref eId="c00011" href="http://www.legislation.gov.uk/id/uksi/2018/942">S.I. 2018/942</ref>
.
</p>
</authorialNote>
and has had regard to the documents and matters referred to in section 104(2)
<authorialNote class="footnote" eId="f00005" marker="5">
<p>
Section 104 was amended by section 58(5) of the Marine and Coastal Access Act
<ref eId="c00012" href="http://www.legislation.gov.uk/id/ukpga/2009/23">2009 (c. 23)</ref>
and by section 128(2) and Schedule 13, paragraphs 1 and 49(1) to (6) of the Localism Act
<ref eId="c00013" href="http://www.legislation.gov.uk/id/ukpga/2011/20">2011 (c. 20)</ref>
.
</p>
</authorialNote>
of the 2008 Act.
</p>
<p>The Secretary of State, having decided the application, has determined to make an order giving effect to the proposals comprised in the application on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.</p>
<formula name="enactingText">
<p>Accordingly, the Secretary of State, in exercise of the powers conferred by sections 114, 115, 120 and 149A of the 2008 Act, makes the following Order—</p>
</formula>
</preamble>
</act>
</akomaNtoso>