I1SCHEDULE 12DOCUMENTS AND PLANS TO BE CERTIFIED
(1) Document Name | (2) Document Reference |
---|---|
Access and rights of way plans | 4.4 |
Book of reference | 3.1 |
Land plans | 4.2 |
Works plans | 4.3 |
Combined heat and power assessment | 5.7 |
Environmental statement | 6.0, 10.6-10.9 |
Design principles statement (appendix 1 of the design and access statement) | 5.6 (appendix 1) |
Flood risk assessment | 6.3.20 |
Outline written scheme of investigation | 7.4 |
Indicative landscape and biodiversity plan | 4.15 |
Landscaping and Biodiversity Management and Enhancement plan | 5.10 |
Indicative surface water drainage plan | 4.13 |
Framework construction environmental management plan | 7.1 |
Framework construction traffic management plan | 7.2 |
Framework construction workers travel plan | 7.3 |
Indicative lighting strategy | 5.11 |
Haul road plans | 4.19 |
Pilfrey laydown plans | 4.20 |
Application guide | 1.2 |
Sch. 12 in force at 29.12.2022, see art. 1