Citation and commencement1

1

This Order may be cited as the East Anglia TWO Offshore Wind Farm (Correction) Order 2022.

2

This Order comes into force on 22nd December 2022.

Corrections2

The East Anglia TWO Offshore Wind Farm Order 2022 is corrected as set out in the table in the Schedule to this Order, in which—

a

column 1 sets out where the correction is to be made;

b

column 2 sets out how the correction is to be made; and

c

column 3 sets out the text which is to be substituted, inserted or omitted.

Signed by authority of the Secretary of State for Business, Energy and Industrial Strategy

David WagstaffDeputy Director Energy Infrastructure PlanningDepartment for Business, Energy and Industrial Strategy