The Network Rail (Cambridge South Infrastructure Enhancements) Order 2022

17.—(1) Before beginning to construct any specified work, Network Rail must submit to the drainage authority plans of the specified work and such further particulars available to it as the drainage authority may within 28 days of the receipt of the plans reasonably require.

(2) Any such specified work must not be constructed except in accordance with such plans as may be approved in writing by the drainage authority, or determined under article 44 (arbitration).

(3) Any approval of the drainage authority required under this paragraph—

(a)must not be unreasonably withheld;

(b)is deemed to have been given if it is neither given nor refused within 2 months of the receipt of the plans for approval or where further particulars are submitted under paragraph (1) within 2 months of the submission of those particulars, and, in the case of a refusal, accompanied by a statement of the grounds of refusal; and

(c)may be given subject to such reasonable requirements as the drainage authority may make for the protection of any drainage work, fishery, water resources, or for the prevention of flooding or pollution or in the discharge of its environmental duties.

(4) The drainage authority must use its reasonable endeavours to respond to the submission of any plans before the expiration of the period mentioned in sub-paragraph (3)(b).