PART 5POWERS OF ACQUISITION
Temporary use of land for maintaining the authorised development29.
(1)
Subject to paragraph (2), at any time during the maintenance period (as defined in paragraph 11) relating to any part of the authorised development, the undertaker may—
(a)
enter on and take temporary possession of any land within the Order limits if such possession is reasonably required for the purpose of maintaining the authorised development; and
(b)
construct such temporary works (including the provision of means of access) and buildings on the land as may be reasonably necessary for that purpose.
(2)
Paragraph (1) does not authorise the undertaker to take temporary possession of—
(a)
any house or garden belonging to a house; or
(b)
any building (other than a house) if it is for the time being occupied.
(3)
Not less than twenty-eight days before entering on and taking temporary possession of land under this article the undertaker must serve notice of the intended entry on the owners and occupiers of the land.
(4)
The undertaker may only remain in possession of land under this article for so long as may be reasonably necessary to carry out the maintenance of the part of the authorised development for which possession of the land was taken.
(5)
Before giving up possession of land of which temporary possession has been taken under this article, the undertaker must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.
(6)
The undertaker must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.
(7)
Any dispute as to a person’s entitlement to compensation under paragraph (6), or as to the amount of the compensation, is to be determined under Part 1 of the 1961 Act.
(8)
Nothing in this article affects any liability to pay compensation under section 152 of the 2008 Act (compensation in case where no right to claim in nuisance) or under any other enactment in respect of loss or damage arising from the carrying out of the authorised development, other than loss or damage for which compensation is payable under paragraph (6).
(9)
Where the undertaker takes possession of land under this article, the undertaker is not required to acquire the land or any interest in it.
(10)
Section 13 of the 1965 Act (refusal to give possession to acquiring authority) applies to the temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.
(11)
In this article “the maintenance period” means the period of 5 years beginning with the date on which the generating station forming Work no.1A first exports electricity to the national electricity transmission network.