Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
14.—(1) No part of the authorised development can commence until a LEMP for that part, substantially in accordance with the outline ecological management plan and illustrative landscape plan, including—
(a)where necessary, measures to protect water voles;
(b)ecological mitigation and enhancement measures;
(c)details of all proposed soft landscaping works, including location, number, species, size and planting density of any proposed planting;
(d)proposed finished ground levels;
(e)details of existing trees to be retained, with measures for their protection during the construction period;
(f)implementation timetables for all ecological and landscaping works; and
(g)maintenance proposals,
has been submitted to and approved by the relevant planning authority in consultation with Natural England.
(2) The authorised development, including maintenance, must be carried out in accordance with the approved LEMP and to a reasonable standard in accordance with the relevant recommendations of appropriate British Standards or other recognised codes of good practice.
Commencement Information
I1Sch. 2 para. 14 in force at 10.3.2022, see art. 1
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: