Article 13
Commencement Information
I1Sch. 4 in force at 10.3.2022, see art. 1
(1) Area | (2) Public right of way | (3) Control or Restriction |
---|---|---|
Thurrock Borough | Station Road within the two areas shown hatched in red on sheet 3 of the access, rights of way and traffic management plans. | Controls on use including marshalling during construction to allow crossing of the highway for construction access. Temporary restriction on all use for up to two weeks at each location, concurrently or consecutively. |
Thurrock Borough | Station Road within the area shown hatched in dark green on sheet 3 of the access, rights of way and traffic management plans. | Controls on use including temporary restrictions on use and partial carriageway closures with traffic management to allow construction of new accesses. |
Thurrock Borough | Footpath through common land connecting Footpath 200 at the location shown hatched in green on sheet 3 of the access, rights of way and traffic management plans. | Controls on use the footpath where it crosses the pipeline route including marshalling during construction and operation to allow installation and maintenance of a gas pipeline. Temporary restriction on all use and diversion during construction. |