SCHEDULE 1E+W+SAuthorised project

PART 3E+W+SRequirements

Control of artificial light emissions during operational phaseE+W+S

25.—(1) Work No. 30 must not begin operation until an operational artificial light emissions management plan providing details of artificial light emissions during the operation of Work No. 30, including measures to minimise lighting pollution and the hours of lighting, has been submitted to and approved by the relevant planning authority.

(2) The approved operational artificial light emissions management plan must be implemented upon, and maintained during, the operation of Work No. 30.

(3) Work No. 41 must not begin operation until an operational artificial light emissions management plan providing details of artificial light emissions during the operation of Work No. 41, including measures to minimise lighting pollution and the hours of lighting, has been submitted to and approved by the relevant planning authority.

(4) The approved operational artificial light emissions management plan must be implemented upon, and maintained during, the operation of Work No. 41.

(5) Work No. 38 must not begin operation until an operational artificial light emissions management plan providing details of artificial light emissions during the operation of Work No. 38, including measures to minimise lighting pollution and the hours of lighting, has been submitted to and approved by the relevant planning authority.

(6) The approved operational artificial light emissions management plan must be implemented upon, and maintained during, the operation of Work No. 38.