SCHEDULE 1Authorised project

PART 3Requirements

Restriction on carrying out grid connection worksI143

No part of the grid connection works may commence under this Order until either—

a

the offshore works have commenced; or

b

the undertaker has provided appropriate evidence to the Secretary of State demonstrating its commitment to commence the authorised development described within paragraph 1 of Schedule 1, Part 1 and the Secretary of State has confirmed that the grid connection works may commence.