5.—(1) The undertaker shall consult with EDF Energy in the preparation of the landfall construction method statement prior to submission of the landfall construction method statement to the relevant planning authority for approval in accordance with requirement 13.
(2) Prior to carrying out Work No. 6, the undertaker shall carry out geophysical surveys to confirm the visible extent of the Coralline Crag formation and shall provide the results of such surveys to the extent that they demonstrate the visible extent of the Coralline Crag to EDF Energy on completion.
(3) The undertaker must not undertake cable trenching activities or locate the HDD punch out within—
(a)the Punch Out and Trenching Restriction Area shown on the Activity Exclusion Zones plan (Drawing No. EA1N-DEV-DRG-IBR-001260); or
(b)the visible extent of the Coralline Crag as confirmed by the surveys undertaken under sub-paragraph (2),
unless otherwise agreed with EDF Energy (such agreement not to be unreasonably withheld or delayed).