The East Anglia TWO Offshore Wind Farm Order 2022

Access to worksE+W+S

13.—(1) The undertaker may, for the purposes of the authorised project—

(a)form and lay out means of access, or improve existing means of access, in the locations specified in columns (1) and (2) of Schedule 6 (access to works); and

(b)with the approval of the relevant highway authority after consultation with the relevant planning authority, form and lay out such other means of access or improve existing means of access, at such locations within the Order limits as the undertaker reasonably requires for the purposes of the authorised project.

(2) If the relevant highway authority fails to notify the undertaker of its decision within 28 days of receiving an application for approval under paragraph (1)(b) that relevant highway authority is deemed to have granted approval.